Grid emission factor: the methodology sets rules for it. CarbonMeld reads it in the project's documents. CM-F-AM0074-GRID-EF
AM0074 — Methodology for new grid connected power plants using permeate gas previously flared and/or vented
About this methodology
Projects use residual gas from natural gas processing, previously flared or vented, to generate electricity. The method measures reductions compared with continued gas disposal and alternative power generation.
- Issued by
- CDM (UNFCCC) · issuer's site
- Version
- 3.0.0 · source ·
- Status
- Active at CDM / UNFCCC · source ·
- Climate outcome
- Emission reductions
- Activity
- Electricity and gas
- Official page
- cdm.unfccc.int ·
How methodology v3 reads projects of this type
What CarbonMeld reads
- shown
A confirmed investment analysis A-INVEST
The documents show a project-level additionality test, the validation confirmed it, and it is an investment analysis (a numeric test of the project's finances with and without carbon revenue).
Deductions that can apply
No additionality test in the documents (renewable energy) A-TEST-NOT-STATED
Renewable energy, power generation and supply: the documents read state no additionality test. A test that the documents do not name is a different case. It takes no points. CarbonMeld applies this rule only where a check of the documents has confirmed its condition; without that check, the rule takes no points.
Set by the methodology or the programme, not assessed by our current method
- not assessed
No legal requirement for the activity: the methodology sets rules for it (AM0074 v03.0.0 baseline identification, p. 2). Our current method does not assess it. CM-F-AM0074-REGULATORY-SURPLUS
- not assessed
Tracking of the end use: the methodology sets rules for it in some cases (AM0074 v03.0.0 applicability, p. 2). Our current method does not assess it. CM-F-AM0074-END-USE-TRACKING
- not assessed
Social safeguards and consent of communities (FPIC): any such rules come from the programme, not the methodology. Our current method does not assess it. CM-F-AM0074-SAFEGUARDS-FPIC
Not applicable to this type — never a gap in our current method
The criterion does not apply to this methodology. Our current method never counts it as a gap.
- CM-N-LEAKAGELeakage
- CM-N-BUFFERBuffer pool
- CM-N-PERMANENCE-REVERSALPermanence and reversals
- CM-N-FNRBFraction of non-renewable biomass (fNRB)
- CM-N-USAGEUsage rate of the devices
- CM-N-DURABILITY-MEASUREMENTDurability of the storage
- CM-N-FEEDSTOCK-SUSTAINABILITYSustainability of the feedstock
The general rules apply as well. Read the general rules.
The rules of methodology v2.2, as they were: the archived v2.2 page.
History and transitions
-
v03.0.0adopted 11 May 2012source
Introduce a new definition of permeate gas; Introduce provisions for the demonstration of use of permeate gas prior to the implementation of the project activity; Introduce provisions for the estimation of costs of permeate gas when …
-
v02adopted 4 Dec 2009source
Include the use of back-up fuels up to 15% on energy basis.
-
v01adopted 28 Nov 2008source
Initial adoption.
Projects using AM0074
Browse 2 published projects using AM0074, listed alphabetically. There is no ranking for this methodology yet: it appears here automatically once 5 of its projects not in the pipeline or under validation are rated. Open a project to view its registry details and the analysis available for that project.
Which registries list projects under AM0074?
In CarbonMeld's data, AM0074 projects are on one registry: CDM (2 projects, 1 registered).
| Registry | Projects | Registered | Projects list |
|---|---|---|---|
| CDM (UNFCCC) | 2 | 1 | See the list |
Counts of project records in CarbonMeld's data, with or without a CarbonMeld analysis. «Registered» counts the records whose current registry status is «registered», as last read (15 November 2026); projects in a later status, such as awaiting verification approval, late to verify or completed, are not in that column.
- Analysis: Re-assessment pending
- Analysis: No rating yet