2.5 MW Bundled Wind Power Project in Maharashtra (India)
Score Breakdown
Integrity
verified Additionality was tested using an investment test and was confirmed by the VVB in the monitoring report.
missing Leakage justification is not addressed, and reversal events are marked as not addressed rather than clearly ruled out.
Transparency
verified The project has a named VVB and a defined monitoring period, with verified emissions reductions reported in the monitoring report.
missing The monitoring report notes missing source documents and incomplete ER sheets, which weakens MRV transparency.
Claim Safety
verified The project is not CORSIA-eligible, which reduces dual-market claim risk.
missing The baseline is project-specific rather than a more conservative standardized baseline, and leakage treatment is unclear.
Documentation
verified Multiple official documents were available, including the PDD, validation report, monitoring report, and issuance-related material.
missing The monitoring report itself says key supporting records were not provided, and the extraction record includes several contradictions across documents.
Detailed Analysis
Integrity
The project’s additionality case is reasonably strong because the monitoring report says additionality was tested through an investment test and verified by the VVB, LGAI Technological Center / Applus+ Certification. The baseline method is project-based, which is acceptable but less robust than a standardized or jurisdictional baseline, and leakage is not addressed in the extracted monitoring record. Reversal risk is not a major issue for a wind project, but the record does not clearly document a buffer pool or a formal reversal treatment.
Transparency
Transparency is mixed. The project has a named verifier and a long monitoring period, and the monitoring report reports 18,410 verified tCO2e, but the same report also says the PP did not provide JMRs, invoices, complete ER sheets, calibration certificates, and other supporting records. That weakens traceability of the verified figure and suggests the MRV package is incomplete.
Claim Safety
Claim safety is moderate to weak because the project is not CORSIA-eligible, which helps, but the baseline is project-specific and leakage is not addressed. The extracted record does not show a quantified leakage deduction or a usage monitoring method, so over-crediting risk cannot be ruled out confidently. The absence of a CCP status also leaves the broader quality label unresolved.
Documentation
Documentation quality is limited by the missing supporting evidence noted by the monitoring report and by the contradictions across documents. The extraction confidence is high, but the report still flags absent technical equipment details, commissioning certificates, PPAs, O&M agreements, calibration certificates, and complete ER sheets. The project documents are also not fully aligned on the crediting period, safeguards, FPIC, leakage treatment, grid factor, and emissions totals.
Overall
I privileged the newer monitoring report for safeguards, FPIC, leakage treatment, and crediting-period information because it is more recent and project-specific, while the older validation report was used only where it appeared to be the only source for the lower emissions figure. The contradictions are material: the record shows different values for credited emissions, different crediting periods, and conflicting statements on safeguards and leakage, so reliability is reduced. Because the project is a wind project with VVB-confirmed additionality but incomplete documentation and unresolved leakage treatment, the overall score is mid-range rather than strong.
Audit Analysis
This is a registered VCS wind project with VVB-confirmed additionality, which supports the core integrity case. However, the monitoring record shows several documentation gaps, leakage is not addressed, and there are material contradictions across documents that reduce confidence in the claimed emissions reductions.
Project Description
Proponent: Raj Infrastructure Development (India) Pvt. Ltd. Protocol categories: Energy industries (renewable/non-renewable sources) Protocols: AMS-I.D. Estimated annual GHG reductions: 3946 tCO2e Region: Asia Registration date: 2010-08-18
Red Flags
- Leakage is not addressed in the monitoring report, and no leakage deduction is stated.
- The monitoring report lists multiple missing supporting documents, including calibration certificates, invoices, JMRs, and complete ER sheets.
- There are contradictions between the older and newer documents on safeguards, FPIC, leakage treatment, grid factor, and credited emissions.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2007 | 2,015 | 0 | 2,015 | |
| 2008 | 3,274 | 2,116 | 1,158 | |
| 2009 | 1,291 | 0 | 1,291 | |
| 2011 | 1,328 | 0 | 1,328 | |
| 2012 | 3,712 | 3,000 | 712 | |
| 2013 | 3,570 | 0 | 3,570 | |
| 2014 | 3,223 | 0 | 3,223 | |
| 2015 | 2,946 | 0 | 2,946 | |
| 2016 | 3,040 | 0 | 3,040 | |
| 2017 | 588 | 0 | 588 | |
| Total | 24,987 | 5,116 | 19,871 |
Cosa migliorerebbe questo punteggio
- Provide the missing source records, including calibration certificates, invoices, JMRs, complete ER sheets, and equipment/commissioning documentation.
- Clarify leakage treatment, reconcile the contradictory emissions and crediting-period figures, and document why the newer monitoring report should override older values.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed investment test
Avoidance project with low reversal risk
Leakage not addressed
Project baseline, reassessment not stated
FPIC and grievance mechanism documented
Not CORSIA-eligible; CCP status not stated
Where to buy
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →