4 MW Bundled Grid Connected Wind Power Project in Tamilnadu, India
#122of 1935 in Renewable energy#59of 975 in India#69of 1459 in CDM (UNFCCC)
Audit Analysis
A 4 MW grid-connected wind project in Tamil Nadu with a VVB-confirmed barrier additionality test and a jurisdictional grid-emission-factor baseline. The project delivered roughly 219% of its pro-rata expectation for the first two-year monitoring period, indicating a conservative baseline, but 18 corrective action requests related to meter calibration and several documentation gaps (FPIC, grievance mechanism, FNRB) temper the overall assessment.
Red Flags
- 18 Corrective Action Requests and 12 Clarification Requests were raised during the first periodic verification, primarily due to energy-meter calibration frequency not matching the registered PDD; a maximum permissible error of 0.5% was applied to measured values.
- Free, Prior and Informed Consent (FPIC) and a formal grievance mechanism are not documented in the extracted record, despite safeguards being mentioned in general terms.
- The leakage justification is inconsistent between the 2008 and 2011 monitoring reports ('quantified' vs 'deemed negligible'), raising a minor data-reliability question.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 5,799 | 0 | 5,799 | |
| 2012 | 13,381 | 0 | 13,381 | |
| Total | 19,180 | 0 | 19,180 |
Risk Indicators
VVB-confirmed barrier test
Avoidance project, no reversal risk
Negligible, justified for grid-connected wind
Jurisdictional grid EF, standardised
Mentioned but FPIC/grievance not documented
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →