9.5 MW wind energy based power generation by Interocean Group
Score Breakdown
Integrity
verified The validation/verification record indicates additionality was confirmed by the VVB using an investment test.
missing Baseline is project-specific and the timing of any baseline reassessment is not stated in available documents.
Transparency
verified Key MRV fields are present, including a defined monitoring period (2017-05-08 to 2019-02-19) and a stated grid emission factor (0.97704).
missing The monitoring report shows a sizable difference between claimed and verified ERs (32,283 vs 28,286), but the extracted record does not provide the reason for the adjustment.
Claim Safety
verified Uses an established CDM small-scale renewable methodology (AMS-I.D, version 18), which generally reduces methodological discretion.
missing CORSIA eligibility and CCP status are not stated in available documents, and leakage treatment is missing, increasing buyer claim and over-crediting risk.
Documentation
verified Core documents are available (PDD, validation report, monitoring report) and extraction confidence is high.
missing Social safeguards elements (FPIC, grievance mechanism, benefit sharing) are not evidenced in the extracted record.
Detailed Analysis
Integrity
The validation/verification record indicates additionality was confirmed by the VVB (KBS) using an investment test, which supports additionality robustness. The baseline is described as project-specific, and the extracted record does not state when (or whether) the baseline was last reassessed, which weakens confidence in baseline validity over time. Leakage is not addressed in the extracted record (no justification and no deduction stated), creating an integrity gap even if leakage is likely low for grid-connected wind.
Transparency
The monitoring report (dated 2021-10-05) provides a clear monitoring period (2017-05-08 to 2019-02-19) and reports a grid emission factor of 0.97704, supporting traceability of calculations. However, the monitoring/verification outcome shows a notable adjustment from 32,283 tCO2e claimed to 28,286 tCO2e verified, and the extracted record does not capture the explanation for this difference. Registry-level completeness is moderate because CORSIA and CCP status are not stated in available documents.
Claim Safety
As an avoidance renewable electricity project under AMS-I.D (version 18), the core quantification approach is standardized, which helps reduce discretionary over-crediting. That said, the absence of any stated leakage treatment in the extracted record and the lack of stated baseline reassessment timing increase uncertainty around conservative crediting. CORSIA eligibility and CCP status are not found in the extracted record, which increases downstream claim risk for buyers seeking specific compliance/quality labels.
Documentation
The extracted record includes three key document types (PDD, validation report, monitoring report) and indicates high extraction confidence, supporting document reliability. No material findings or corrective actions are reported in the extracted record, which is a positive signal for audit outcomes. However, safeguards-related elements (FPIC, grievance mechanism, benefit sharing) are not evidenced in the extracted record, reducing completeness for non-carbon integrity expectations.
Overall
No contradictions were identified in the extracted record, so no score adjustments were required for internal document inconsistencies. The project scores strongest on having a VVB-confirmed additionality test and a standard CDM methodology, but is pulled down by missing leakage treatment and missing baseline reassessment information. The sizable claimed-versus-verified ER difference also increases perceived MRV sensitivity, lowering claim safety and transparency relative to documentation completeness.
Audit Analysis
This CDM wind project has a clear avoidance crediting logic and additionality was confirmed by the VVB using an investment test. However, leakage is not addressed in the extracted record and the baseline is project-specific with no stated reassessment timing, which increases over-crediting uncertainty. Documentation coverage is reasonably good (PDD, validation, monitoring) with high extraction confidence, but safeguards and grievance provisions are not evidenced.
Project Description
The project activity has been undertaken to harness the available wind power potential to generate clean power in Madhya Pradesh. The project activity will install and operate 5 number of sophisticated, state-of art Wind Turbine Generators (WTG) consisting of 4*2000kW and 1*1500kW with aggregated installed capacity of 9.5 MW. The project will generate approximately 18470 MWh of electricity per annum, which will be sold to state electricity board of Madhya Pradesh states of India. All the WTGs of proposed project activity are connected to NEWNE regional grid of India. The project activity will help in green house gas (GHG) emission reduction by using renewable resources (wind energy) for generating power which otherwise would have been generated using grid mix power plants, which is dominated by fossil fuel based thermal power plants. The project activity is a green field project aimed at utilising wind to produce power.
Red Flags
- Leakage is not addressed in the extracted record (no justification and no stated deduction), despite being a required element to explicitly treat under CDM monitoring/verification narratives.
- Large gap between claimed and verified emission reductions (32,283 claimed vs 28,286 verified) indicates material adjustments and raises MRV/QA sensitivity.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2023 | 28,286 | 0 | 28,286 | |
| Total | 28,286 | 0 | 28,286 |
Cosa migliorerebbe questo punteggio
- Provide explicit leakage assessment and conclusion (including a stated leakage deduction of 0% with justification, if applicable) in the monitoring/verification narrative.
- Disclose baseline update/reassessment information (or confirm applicability of the grid emission factor vintage and any required updates) and publish the reason for the claimed-versus-verified ER adjustment.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed investment test
Avoidance project (no reversal pool needed)
Leakage not addressed in record
Project-specific; reassessment timing missing
No FPIC/grievance evidenced
CORSIA/CCP status not stated
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →