9.6 MW Wind Energy Project at Jamvadi & Navagam & Kalavad, Jamnagar, Gujarat, India of Rohit Surfactants Pvt. Ltd.
Score Breakdown
Integrity
verified Additionality was confirmed by the VVB using an investment test, which supports the project's core eligibility case.
missing Leakage was not addressed in the monitoring report, and the baseline is project-based rather than a recently reassessed standardized baseline.
Transparency
verified The project has a named VVB, a defined monitoring period, and Gold Standard registry context, which helps traceability.
missing The verification report lists several CARs and missing supporting evidence, and the extracted record does not state total claimed or verified emission reductions.
Claim Safety
verified The project is a wind energy activity under Gold Standard, which generally lowers reversal risk compared with land-based projects.
missing Leakage justification is not addressed, and the record shows CORSIA eligibility while CCP status is not stated, leaving some claim-channel ambiguity.
Documentation
verified The record includes both monitoring and PDD evidence, and the VVB is identified as LGAI Technological Center, S.A.
missing The extraction confidence is only medium, and the verification report explicitly says several supporting documents were missing.
Detailed Analysis
Integrity
The verification report confirms additionality through an investment test and identifies no reversal events, which supports the project's core environmental case. However, the baseline is described only as project-based, the leakage treatment is not addressed, and the monitoring record does not provide a buffer pool or other permanence backstop. These gaps reduce confidence in the robustness of the credited reductions.
Transparency
The project is tied to Gold Standard and has a named VVB, with a clear monitoring period from 2018-10-21 to 2020-12-31. But the extracted record does not state total emission reductions claimed or verified, and the verification report lists multiple CARs and missing source documents. That combination points to only moderate transparency.
Claim Safety
Wind projects have inherently low reversal risk, and the record shows no reversal events reported. Still, leakage is not addressed despite a zero deduction, and CORSIA eligibility is marked true while CCP status is not stated, so the claim stack is not fully clean. The missing quantified FNRB and usage-rate fields also limit confidence in over-crediting risk assessment.
Documentation
The evidence set includes the monitoring report and PDD, and the VVB is identified, which is a positive sign. Even so, the extraction confidence is only medium, and the verification report explicitly notes missing commissioning certificates, technical specifications, calibration details, and emission-reduction support. Those omissions materially weaken documentation quality.
Overall
I privileged the monitoring report and verification report where they were more specific and recent, but the record still contains contradictions that lower reliability. In particular, the monitoring report says leakage is not addressed, while another extracted source suggests it was quantified; I gave priority to the explicit monitoring-report statement because it is the more direct source for MRV treatment. I also privileged the later monitoring-period definition over the earlier one, since the contradiction concerns the crediting period and the later report appears to reflect the updated issuance context. The project is credible enough to avoid a low score, but the missing evidence and unresolved MRV issues keep it in the middle range.
Audit Analysis
This is a real wind project with VVB-confirmed additionality and no reversal events reported, but the evidence package is incomplete and several key monitoring details are missing. Leakage is not addressed, the baseline is project-based rather than a more robust standardized baseline, and the verification file contains multiple corrective actions that weaken confidence in the claimed reductions.
Project Description
Developer: EKI Energy Services Limited Type: Wind Size: Small Scale Methodology: AMS-I.D. Grid connected renewable electricity generation Crediting period: 2018-02-01 → 2021-09-07 Estimated annual credits: 17983 tCO2e SDGs: Goal 7: Affordable and Clean Energy, Goal 13: Climate Action, Goal 8: Decent Work and Economic Growth
Red Flags
- Leakage was not addressed, and the monitoring record does not provide a justification for the zero leakage deduction.
- The verification report raised multiple corrective actions, including missing supporting documents for emission reductions, commissioning, technical specifications, and calibration.
Credit Vintages
Nessuna emissione registrata sul registro.
Cosa migliorerebbe questo punteggio
- Provide a complete MRV package with emission-reduction calculations, supporting invoices/JMRs, calibration certificates, and the missing commissioning and technical specification documents.
- Clarify leakage treatment, reconcile the crediting-period discrepancy, and publish the final verified emission reductions alongside registry and claim-status information.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed investment test
Wind project; no reversals reported
Leakage not addressed
Project baseline only
FPIC and grievance present, but incomplete safeguard documen
CORSIA-eligible; CCP status not stated
Where to buy
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →