Catalytic N2O Abatement Project in the Tail Gas of the Nitric Acid Plant of the Pakarab Fertilizer Ltd (PVT) in Multan, Pakistan
#147of 189 in Methane#6of 9 in Pakistan#1317of 1459 in CDM (UNFCCC)#6of 6 in ACM0019
Audit Analysis
A CDM N2O abatement project at a Pakistani nitric acid plant with a VVB-confirmed barrier additionality test and a project-specific modeled baseline. The validation report (April 2022) flagged five material findings and nine corrective actions covering PDD compliance, ER spreadsheet errors, and missing supporting documents, and no monitoring-period data is available to verify the 4.6 million ERR claimed over the seven-year crediting period. The combination of data-quality gaps, a low-confidence extraction, and the absence of any verified performance data limits confidence in the project's integrity and claim safety.
Red Flags
- Five material findings (CARs) in the validation report include abatement-efficiency mismatch, leap-year calculation errors, and missing production data for Line C in 2021–2022, indicating the ERR calculation may be unreliable until corrected.
- No monitoring-period data or verified ERR figure is available in the extracted record, so the 4,599,180 ERR claimed over the 2021–2028 crediting period cannot be cross-checked against actual performance.
- Contradiction on leakage treatment: the PDD (2022-04-07) states leakage is 'deemed negligible' while an undated appendix describes it as 'quantified,' leaving the actual leakage deduction ambiguous.
- Minimum extraction confidence is rated low and one of the four source documents is listed as 'unknown,' reducing confidence in the completeness of the evidence base.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2008 | 962,221 | 0 | 962,221 | |
| 2009 | 761,349 | 0 | 761,349 | |
| 2010 | 591,192 | 0 | 591,192 | |
| 2011 | 943,943 | 0 | 943,943 | |
| 2012 | 457,994 | 0 | 457,994 | |
| 2013 | 208,164 | 0 | 208,164 | |
| 2017 | 175,219 | 0 | 175,219 | |
| Total | 4,100,082 | 0 | 4,100,082 |
Risk Indicators
VVB-confirmed barrier test; capture not legally required
no reversal e
0% deduction deemed negligible but contradicted by appendix
Project-specific modeled baseline; reassessed 2022
FPIC, grievance mechanism, and safeguards not found in recor
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →