Combined cycle electricity generation activity at Gurgaon, India
#839of 975 in India#1290of 1459 in CDM (UNFCCC)#46of 72 in AMS-II.I
Audit Analysis
A CDM combined-cycle power project in Gurgaon, India, validated by DNV with a confirmed investment additionality test, but the validation report carried three corrective action requests covering benchmark justification, monitoring plan completeness, and baseline calculation methodology. The extracted record contains a ten-fold discrepancy in the claimed emission reduction figure between the PDD and the validation report, and no monitoring-period data, verified ERR, or buffer pool information was found in the available documents.
Red Flags
- Ten-fold discrepancy in total ERR between the PDD (412,110 tCO2e) and the validation report (41,211 tCO2e), indicating a probable transcription error but raising data-reliability concerns
- Three corrective action requests (CARs) were raised at validation covering benchmark selection, monitoring plan QA/QC, and baseline grid-vs-captive-power calculation, meaning the project was not validated without conditions
- Leakage deduction of 0% justified only as 'deemed negligible' without a quantitative or methodological explanation in the available documents
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
no reversal events but no explicit permanenc
0% deduction, 'deemed negligible' without quantitative justi
Project-specific baseline; CAR raised on grid-vs-captive cal
Safeguards and benefit sharing mentioned; no FPIC or grievan
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →