Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia
#2of 10 in Bolivia#950of 1459 in CDM (UNFCCC)#5of 8 in ACM0007
Audit Analysis
A CDM energy-efficiency project converting an open-cycle gas turbine to combined cycle at Guaracachi, Bolivia, using the standard ACM0007 methodology. The project has a barrier additionality test and a project-specific baseline reassessed at the start of its 7-year crediting period, but suffers from significant data gaps: identical claimed and verified ERR figures with no stated monitoring period, a 0% leakage deduction with contradictory justifications across documents, and 11 material findings (all resolved) in the monitoring report. The absence of FNRB, usage-rate data, CORSIA/CCP status, and safeguards documentation limits confidence in the credit's robustness.
Red Flags
- Identical claimed and verified ERR (165,708 tCO₂e) with no stated monitoring period — cannot confirm actual delivery versus ex-ante estimate
- Leakage justification contradicts between the monitoring report ('quantified') and the validation report ('deemed negligible'), undermining confidence in the 0% deduction
- 11 material findings in the monitoring report, including calculation errors in Build Margin and Operating Margin emission factors and in the GHG reduction calculation, indicating initial documentation quality issues
- No buffer pool, no FNRB value, no usage-rate data, and no CORSIA or CCP eligibility status found in any available document
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 192,397 | 0 | 192,397 | |
| 2016 | 547,630 | 0 | 547,630 | |
| 2019 | 356,766 | 0 | 356,766 | |
| Total | 1,096,793 | 0 | 1,096,793 |
Risk Indicators
Barrier test applied; VVB confirmation not explicitly stated
low inherent reversal risk for infrastructur
0% deduction with contradictory justification across documen
Project-specific baseline; reassessed 2017 at crediting peri
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →