Dissemination of improved stoves (Mogogo) in the Eritrean highlands
GS-1173 ↗ · current registry ID: GS748
#1047of 1329 in Industrial#34of 38 in Eritrea#1492of 1801 in Gold Standard (GS)
Audit Analysis
This Gold Standard cookstove project in Eritrea delivered only about 48% of its PDD-estimated emission reductions, with a declining verified usage rate and no buffer pool in place. Seven data contradictions across documents—including conflicting FNRB methods, leakage justifications, and additionality test types—undermine confidence in the underlying data. The absence of a named VVB and a verified ERR figure further weakens the transparency and claim-safety profile.
Red Flags
- Actual emission reductions (4,891 tCO2e) were less than half the PDD estimate (10,220 tCO2e), attributed to fewer stoves installed and adjusted fuel savings (monitoring report, 2020).
- Verified usage rate declined from 0.991 (2014 monitoring report) to 0.90 (2020 monitoring report), falling below the 0.96 assumed in the PDD.
- No buffer pool percentage is stated in any available document, and reversal events are marked as 'not addressed' despite the cookstove asset having a finite service life.
- The FNRB method is reported as 'national default' in the 2020 monitoring report but 'local field' measurement in the PDD (2010), a material discrepancy that could affect the baseline.
- The VVB name is not stated in any extracted document, and additionality verification by the VVB is not confirmed.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 1,271 | 1,271 | 0 | |
| 2010 | 3,166 | 3,166 | 0 | |
| 2011 | 2,720 | 2,720 | 0 | |
| 2012 | 2,684 | 2,684 | 0 | |
| 2013 | 2,553 | 2,553 | 0 | |
| 2014 | 2,222 | 2,222 | 0 | |
| 2015 | 2,344 | 2,323 | 21 | |
| 2016 | 2,697 | 2,644 | 53 | |
| 2017 | 2,682 | 2,629 | 53 | |
| 2018 | 2,108 | 2,108 | 0 | |
| 2019 | 1,254 | 1,254 | 0 | |
| Total | 25,701 | 25,574 | 127 |
Risk Indicators
Combined test in PDD but VVB confirmation not stated
reversal events not addressed
0% deduction; justification inconsistent across reports
Project-specific; FNRB method contradicts between PDD and monitoring
Safeguards and benefit-sharing mentioned; FPIC and grievance mechanism not stated
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →