Grid connected hydro power project in Sri Lanka
#1524of 1935 in Renewable energy#9of 10 in Sri Lanka#1304of 1459 in CDM (UNFCCC)
Audit Analysis
A grid-connected hydro avoidance project in Sri Lanka validated by SGS UK in 2012 under CDM methodology AMS.I.D. Additionality is confirmed via an investment test and the baseline is jurisdictional per the validation report, but seven material findings (CARs) were raised during validation covering investment-analysis inconsistencies, benchmark-calculation errors, and project-capacity discrepancies. No monitoring or verification reports are available in the extracted record, and the overall extraction confidence is low, leaving the project's actual performance unverified.
Red Flags
- Seven material findings (CARs) raised during validation, including inconsistencies in the investment analysis (financing currency, interest rate, O&M costs) and benchmark/sensitivity-analysis calculations, which undermine confidence in the additionality claim
- No monitoring or verification reports are present in the extracted record; the project's actual emissions reductions over its 2012–2022 crediting period are unverified
- Baseline method is stated as 'jurisdictional' in the validation report but 'project' in the PDD — an unresolved contradiction between the two key documents
- Minimum extraction confidence is rated 'low', indicating at least one key document was poorly readable and the structured data may be incomplete
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
Negligible, justified for grid-connected hydro
Jurisdictional per VVB, but contradicted by PDD
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →