GS1247 VPA 37 Improved Kitchen Regimes - Dowa Boreholes, Malawi
GS-626 ↗ · current registry ID: GS3561
#698of 1329 in Industrial#52of 92 in Malawi#1048of 1801 in Gold Standard (GS)
Audit Analysis
This Gold Standard borehole project in Malawi has a VVB-verified additionality assessment and no reported reversal events, but is undermined by an extraordinary volume of material findings, multiple borehole failures, water quality issues, parameter caps imposed through a grievance review, and significant contradictions across documents on leakage, fNRB, and ERR figures. The project-specific baseline, 0% leakage deduction (contradicting the PDD's 5%), and the absence of CORSIA/CCP clarity leave meaningful over-crediting and greenwashing risk. Documentation is extensive in volume (47 documents) but poor in quality, with dozens of open corrective actions, registry errors, and formatting inconsistencies.
Red Flags
- Dozens of material findings and corrective actions remain open or were raised during verification, including non-functional boreholes, water quality test failures, and parameter caps imposed via a GS grievance review
- Leakage deduction of 0% (deemed negligible) in the 2026 verification contradicts a 5% deduction in the 2023 PDD, with no clear reconciliation
- fNRB value of 0.94 (local field, 2026) contradicts 0.81 (national default, 2019 monitoring report), and the method itself shifted between documents
- 25 boreholes in Kasungu district retired from the project due to SHA exit plan; multiple additional boreholes non-functional or running dry during 2025
- Registry reflects incorrect methodology (TPDDTEC v1) and SDGs for some VPAs; correction request still pending
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 3,144 | 3,144 | 0 | |
| 2014 | 10,000 | 10,000 | 0 | |
| 2015 | 10,000 | 10,000 | 0 | |
| 2016 | 10,000 | 6,516 | 3,484 | |
| 2017 | 10,000 | 9,584 | 416 | |
| 2018 | 9,973 | 3,448 | 6,525 | |
| 2019 | 9,471 | 7,922 | 1,549 | |
| 2020 | 8,427 | 8,427 | 0 | |
| 2021 | 7,188 | 3,916 | 3,272 | |
| 2022 | 10,000 | 9,800 | 200 | |
| 2023 | 8,770 | 0 | 8,770 | |
| 2024 | 9,577 | 0 | 9,577 | |
| Total | 106,550 | 72,757 | 33,793 |
Risk Indicators
VVB-confirmed combined test
borehole failures and retirements
0% deduction; contradicts PDD 5%
Project-specific; reassessed 2020
FPIC and grievance present; safeguards inconsistent
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →