Huaibin MSW Landfill Site LFG Recovery and Comprehensive Utilization Project

VCS-2728 ↗

#643of 1084 in China#715of 1339 in Verra (VCS)#63of 159 in ACM0001

5.0/ 10
Integrity
5.0
Transparency
5.0
Claim Safety
5.5
Documentation
4.5

Audit Analysis

This VCS landfill gas recovery project (ACM0001 v19.0) has VVB-verified additionality and no permanence risk, and its verified emissions reductions align closely with the pro-rata lifetime expectation. However, the verification report identified 12 material findings and 12 corrective actions, and several critical parameters (grid emission factor, legally-required capture, additionality test type) show contradictions across documents, undermining confidence in the robustness of the credit claims.

Red Flags

  • 12 material findings in the verification report, including inconsistent baseline emission calculations between the monitoring report and the ER sheet, and missing rationale for methane density assumptions
  • Grid emission factor contradiction: the verification report uses 0.57205 (2019) while the monitoring report uses 0.8587 — a 50% discrepancy that directly affects credit quantities
  • Contradiction on whether LFG capture is legally required: the verification report states true, the monitoring report states false — if legally required, additionality is fundamentally weakened
  • 12 corrective actions remain required, including cross-checking ER sheet and MR values, justifying methane density, and updating GWP values
  • Minimum extraction confidence rated low, indicating at least one key document was poorly readable

Credit Vintages

IssuedRetiredAvailable
2020
31,01021,4859,525
2021
58,415058,415
2022
29,501029,501
Total118,92621,48597,441

Risk Indicators

Additionality

VVB-verified but legally-required capture contradiction unresolved

Permanence

Not AFOLU; no reversal risk applicable

Leakage

0% deduction, deemed negligible for LFG capture

Baseline

Project-specific measured baseline; reassessment not yet due (2030)

Safeguards

FPIC conducted, grievance mechanism present, safeguards mentioned

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-02ACM0001

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents