The Linshu Biogas Recovery project is a VCS-registered biogas-to-power project with a VVB-confirmed investment additionality test and no material findings, but it relies on a project-specific baseline, a 0% leakage deduction whose justification shifted between documents, and an aging 2019 grid emission factor. One corrective action was raised, and several key parameters (buffer pool, CORSIA/CCP status, usage monitoring) are not stated in the available record.
Red Flags
- Leakage justification changed from 'quantified' in the validation report (2021) to 'deemed negligible' in the monitoring report (2023) while the deduction remained 0%, weakening the original quantification
- Grid emission factor of 0.7119 tCO2/MWh is from 2019, more than three years before the 2022–2023 monitoring period, risking over- or under-estimation of displaced emissions
- One corrective action (CAR) was identified in the verification report, indicating a non-conformity that required remediation
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2019 | 31,515 | 13,157 | 18,358 | |
| 2020 | 414,641 | 288,854 | 125,787 | |
| 2021 | 394,577 | 392,304 | 2,273 | |
| 2022 | 224,548 | 221,884 | 2,664 | |
| 2023 | 35,762 | 5,762 | 30,000 | |
| Total | 1,101,043 | 921,961 | 179,082 |
Risk Indicators
VVB-confirmed investment test
avoidance project
0% deduction; justification shifted across docs
Project-specific; not yet due for reassessment
FPIC conducted; grievance mechanism present
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →