Shandong Taipingshan Wind Farm Project
Score Breakdown
Integrity
verified The validation/verification record indicates additionality was confirmed by the VVB using an investment test.
missing Baseline and key quantification inputs show inconsistencies across documents (including grid emission factor and crediting period), weakening confidence in the baseline and ER quantification.
Transparency
verified A named VVB is provided and the monitoring period is clearly stated (2020-04-27 to 2021-12-31) in the monitoring report (2022).
missing Multiple contradictions across official documents (ER totals, safeguards fields, grid factor, crediting period) reduce transparency and traceability.
Claim Safety
verified The project is explicitly not CORSIA-eligible in the extracted record, reducing aviation-claim channel risk.
missing Over-crediting risk is elevated by conflicting ER figures and grid emission factors across documents, plus unresolved corrective actions tied to metering and start dates.
Documentation
verified A relatively complete document set is referenced (PDD, monitoring report, validation report, issuance) with 27 documents used and high extraction confidence.
missing Numerous corrective actions were required (including LoAs, metering issues, and inconsistent dates), indicating documentation gaps at verification/issuance readiness.
Detailed Analysis
Integrity
The validation/verification record confirms additionality via an investment test and indicates it was confirmed by the VVB. However, the baseline is project-specific (ACM0002) and the extracted record does not show when the baseline was last reassessed, which is a robustness gap. Integrity is further weakened by contradictions in key quantification inputs (e.g., grid emission factor differs between the monitoring report (2022) and a validation report (2021)), and by corrective actions in the monitoring report (2022) related to start-date consistency and main meter issues.
Transparency
The monitoring report (2022-10-28) provides a clear monitoring period (2020-04-27 to 2021-12-31) and identifies the VVB as LGAI Technological Center, S.A. (Applus+ Certification). At the same time, transparency is undermined by multiple cross-document inconsistencies (ER totals, safeguards fields, grid factor, and crediting period), making it difficult to reconcile what was actually monitored and credited. The monitoring report (2022) also lists several corrective actions requesting additional evidence (e.g., calibration details for meters), which suggests MRV documentation was not fully complete at the time of review.
Claim Safety
The extracted record states the project is not CORSIA-eligible, which reduces the risk of high-impact aviation-related claims. Nonetheless, claim safety is weakened by conflicting emissions reduction figures across documents (including a large discrepancy in verified ERs) and by a conflicting grid emission factor between the monitoring report (2022) and a validation report (2021), both of which can materially affect credited volumes. Leakage is not addressed in the extracted record (no justification and no stated deduction), which adds uncertainty even if leakage is often low for grid-connected wind projects.
Documentation
The extracted record references a broad set of evidence documents (including PDD, monitoring report, validation report, and issuance) and indicates 27 documents were used with high extraction confidence. However, the monitoring report (2022) lists numerous corrective actions, including requests for DNA letters of approval, inconsistencies in key dates, and missing/unclear calibration information for meters, indicating documentation and evidentiary completeness issues. These gaps reduce confidence that all eligibility and MRV requirements were consistently evidenced across the project record.
Overall
Overall quality is moderate: additionality is VVB-confirmed, but the project record contains several material contradictions that increase over-crediting and eligibility-boundary risk. For ER quantities, I privilege the more recent monitoring/verification context where available (e.g., the monitoring report dated 2022-10-28 for the 2020–2021 monitoring period), but the presence of a conflicting verified ER figure in a 2021 document (307,768 vs 124,141) indicates reliability issues that warrant a score penalty. For the crediting period, I privilege the monitoring report (2022) stating 2020–2030 over the earlier monitoring document (2021) stating 2010–2020 because it aligns with the stated monitoring period starting 2020-04-27, yet the contradiction itself remains a significant red flag. For safeguards-related fields (FPIC, grievance mechanism, benefit sharing), I privilege the newer monitoring report (2022) over the older monitoring report (2013), but treat this as a documentation consistency issue rather than a clear improvement, and score conservatively.
Audit Analysis
This is a VCS wind power project using ACM0002 with additionality confirmed by the VVB, but several internal inconsistencies across documents raise reliability and over-crediting concerns. Leakage treatment is not addressed in the extracted record, and multiple corrective actions were raised around start dates and metering/calibration evidence.
Project Description
The Shandong Taipingshan Wind Farm Project is a 49.3MW wind farm located in Weifang City, Shandong Province, P. R. China. By generating electricity through wind resources, the project will reduce greenhouse gas (GHG) emissions by replacing fossil-fuel dominated electricity from North China Power Grid. The project involves the installation of 58 wind turbines with a total installed capacity of 49.3MW.
Red Flags
- Large inconsistencies in reported/verified emission reductions across documents (e.g., verified ERs reported as 307,768 vs 124,141).
- Crediting period is inconsistent across monitoring documents (2010–2020 vs 2020–2030), creating uncertainty about eligibility and vintage boundaries.
- Leakage is not addressed in the extracted record (no justification and no stated deduction).
- Corrective actions include start-date inconsistencies and metering/calibration issues, which are central to MRV accuracy.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 49,013 | 49,013 | 0 | |
| 2011 | 97,696 | 97,696 | 0 | |
| 2012 | 92,076 | 92,076 | 0 | |
| 2014 | 83,903 | 79,010 | 4,893 | |
| 2015 | 87,193 | 63,489 | 23,704 | |
| 2016 | 83,316 | 83,316 | 0 | |
| 2017 | 83,439 | 83,439 | 0 | |
| 2018 | 81,164 | 81,164 | 0 | |
| 2019 | 81,816 | 81,816 | 0 | |
| 2020 | 28,925 | 28,925 | 0 | |
| Total | 768,541 | 739,944 | 28,597 |
Cosa migliorerebbe questo punteggio
- Provide a reconciled ER accounting table that explains the differences between claimed and verified ER figures across the 2021 and 2022 documents, with clear linkage to issuance records.
- Resolve and document the definitive crediting period and project start date with primary evidence, and ensure all monitoring meters have complete calibration/traceability information in the monitoring report.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed investment test
Avoidance project; no reversal risk indicated
Leakage not addressed in record
Project-specific baseline; reassessment timing unclear
Safeguards reported but inconsistent across years
Not CORSIA-eligible; CCP status not stated
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →