A registered VCS biogas project in China with VVB-confirmed additionality and a grievance mechanism, but undermined by 16 material findings (including calculation errors and unit inconsistencies), a massive gap between ex-ante and verified emissions reductions (only ~4% of pro-rata expectation delivered in year one), and low extraction confidence across the document set. The under-delivery is conservative for buyers but raises questions about the robustness of the original baseline estimate.
Red Flags
- Verified ERR of 4,026 tCO2e is only ~3.9% of the pro-rata expectation (102,700 tCO2e) for the first monitoring year, suggesting the ex-ante estimate was highly optimistic or the plant operated far below design capacity
- 16 material findings in the verification report, including incorrect GWP values (AR6 used instead of AR5), flare efficiency calculation errors, unit inconsistencies, and missing SPECflare values — all closed but indicative of weak initial documentation quality
- FPIC was not conducted and benefit sharing is contradicted between the PDD (described) and the validation report (not described), leaving community engagement status unclear
- No buffer pool percentage or permanence mechanism is stated in the available documents, leaving reversal risk unaddressed despite the 10-year crediting period
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable, reducing reliability of the extracted record
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 527 | 0 | 527 | |
| 2022 | 3,499 | 0 | 3,499 | |
| Total | 4,026 | 0 | 4,026 |
Risk Indicators
VVB-confirmed investment test
avoidance project
0% deduction, 'quantified' justification only
Project-specific, modeled, no reassessment date
Grievance present; FPIC not conducted; benefit sharing contr
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →