Tree Plantation Programme in Different States of India Phase 1

ICR-172 ↗

#52of 80 in ARR (afforestation)#8of 9 in IN#93of 154 in Intl. Carbon Registry (ICR)

3.9/ 10
Integrity
4.5
Transparency
4.0
Claim Safety
3.0
Documentation
3.5

Audit Analysis

This Indian tree-plantation project (ICR-172) has a VVB-confirmed additionality test and a 10% buffer pool, but is undermined by 17 material findings, a project-specific baseline with unresolved land-use contradictions, and an extremely low verified delivery of roughly 1.3% of the pro-rata ex-ante expectation for the elapsed monitoring period. The contradictions between the validation report and the issuance record on both claimed and verified ER figures, combined with 13 outstanding corrective actions, raise serious concerns about data reliability and the robustness of the underlying sequestration claims.

Red Flags

  • Verified ER of 12,723 tCO2 represents only ~1.3% of the pro-rata ex-ante expectation (~967,660 tCO2) for the 5.9-year monitoring period, indicating severe under-delivery or an overly optimistic ex-ante estimate
  • Contradiction between validation report (claimed = verified = 11,450) and issuance record (claimed = 163,450, verified = 12,723) on both total_err_claimed and total_err_verified
  • 17 material findings including a contradiction in baseline and leakage descriptions regarding land use, missing sources for existing land conditions, and justification required for Mahogany growth in non-native regions
  • Monitoring plan initially did not account for dead or cut trees, and the parameter 'Project trees' was incorrectly listed as a constant rather than a monitored variable
  • Contradiction in tree counting methodology (drone vs physical) within the VVB report itself

Credit Vintages

IssuedRetiredAvailable
2021
2,26802,268
2022
6,12506,125
2023
12,333012,333
2024
20,057020,057
2025
32,284032,284
2026
51,965051,965
2027
83,644083,644
2028
134,6330134,633
2029
216,7060216,706
2030
348,8110348,811
2031
561,4490561,449
2032
903,7110903,711
2033
77,764077,764
Total2,451,75002,451,750

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

10% buffer, no reversals, but monitoring gap for dead trees

Leakage

0% deduction, but land-use contradiction in baseline/leakage descriptions

Baseline

Project-specific, Mahogany suitability and land-condition sources unresolved

Safeguards

FPIC and benefit sharing documented; grievance mechanism not stated

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-08General Methodology v2.1

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents