UPGRADE OF DOMINICAN POWER PARTNERS’ LOS MINA POWER STATION FROM OPEN CYCLE TO COMBINED CYCLE POWER GENERATION

VCS-1103 ↗

6.9 / 10
Integrity
6.6
Transparency
7.2
Claim Safety
6.8
Documentation
7.6

Score Breakdown

Integrity

verified The validation/verification record indicates additionality was assessed using an investment test and confirmed by the VVB.

missing Leakage is said to be quantified, but the leakage deduction value and baseline reassessment timing are not found in the extracted record.

Transparency

verified Multiple core documents are available (PDD, validation report, monitoring report, issuance) and the VVB is identified (Applus+).

missing Claimed vs verified ERs differ (1,202,884 vs 1,144,395) and some key parameters (e.g., leakage deduction) are not clearly reported in the extracted record.

Claim Safety

verified The project is explicitly not CORSIA-eligible, reducing certain downstream aviation-claim risks.

missing Project-specific baseline and missing leakage deduction value increase over-crediting/claims uncertainty.

Documentation

verified Document set is relatively complete (8 documents used) with high extraction confidence and no reported corrective actions.

missing Contradictions between the PDD/validation report and the monitoring report (crediting period, safeguards, grievance mechanism) reduce document consistency.

Detailed Analysis

Integrity

The monitoring/verification record indicates additionality was demonstrated via an investment test and confirmed by the VVB (monitoring report, 2022). The baseline is project-specific under ACM0007, but the timing of any baseline reassessment is not stated in the extracted record (monitoring report, 2022; PDD, 2013). Leakage is described as quantified, yet the actual leakage deduction percentage is not found, which weakens confidence in net ER conservativeness (monitoring report, 2022). No material findings or corrective actions are reported in the extracted record (monitoring report, 2022).

Transparency

Core project documentation appears available across the project lifecycle (PDD 2013, validation report 2013, monitoring report 2022, and issuance records). The monitoring period is clearly stated as 2017-04-01 to 2021-10-31 (monitoring report, 2022). A notable transparency signal is the gap between claimed and verified ERs (1,202,884 claimed vs 1,144,395 verified), but the extracted record does not provide enough detail here to fully explain the adjustment (monitoring report, 2022). Some key quantified items (e.g., leakage deduction) are not clearly captured in the extracted record, limiting reproducibility.

Claim Safety

The project is explicitly not CORSIA-eligible, which lowers the risk of contentious aviation-related claims (monitoring report, 2022). However, over-crediting risk remains moderately elevated because the baseline is project-specific and the extracted record does not show when the baseline was last reassessed (PDD, 2013; monitoring report, 2022). The difference between claimed and verified ERs suggests the verifier applied adjustments or conservativeness, but it also signals that headline claims based on “claimed” numbers would be unsafe (monitoring report, 2022). CCP status is not found in the extracted record, leaving uncertainty about alignment with higher-integrity labels.

Documentation

The extracted record draws on a reasonably complete set of documents (PDD, validation report, monitoring report, issuance) with high extraction confidence and 8 documents used. The VVB is identified as LGAI Technological Center, S.A. (Applus+ Certification) (monitoring report, 2022). No corrective actions are reported in the extracted record, which supports document quality for the period assessed (monitoring report, 2022). Nonetheless, internal consistency issues across documents (notably safeguards/grievance and crediting period dates) reduce documentation reliability.

Overall

Overall quality is moderately strong but constrained by missing quantified leakage treatment and baseline reassessment timing, plus several cross-document inconsistencies. For safeguards and grievance mechanism, the monitoring report (2022) states they are present, while the validation report (2013) indicates they were not; the more recent monitoring report is privileged as it reflects later implementation, but the inconsistency still reduces confidence in continuous safeguards management. For the crediting period, the monitoring report (2017–2027) conflicts with the PDD (2016–2025); the monitoring report is privileged as the later operational/issuance-aligned document, but the discrepancy suggests either a renewal/revision not clearly tracked in the extracted record. These contradictions warrant a downward adjustment to transparency/documentation and caution in external claims.

Audit Analysis

This VCS avoidance project has a reasonably robust integrity case, with additionality confirmed by the VVB and no material findings or corrective actions reported in the extracted record. However, key quantitative elements (notably leakage deduction and baseline reassessment timing) are missing, and several cross-document inconsistencies reduce confidence in the reliability of non-quantitative disclosures.

Project Description

The proposed project includes construction of a Heat Recovery Steam Generators (HRSGs) that will take advantage of the open cycle generation of the existing natural gas based power plant in Los Mina to produce steam, which will in turn be used to power a 108 MW steam turbine. Los Mina power plant currently includes two 105 MW units, with average historical production of 80MW each, due to grid system requirement. The total capacity of the plant will increase from 210 MW to an expected 318 MW. The potential GHG emissions reduction are based on the fact that electricity generated by the project activity using HRSGs will offset electricity from the national grid which is highly fuel oil and open-cycle based. Furthermore, the project enables a higher supply of energy to the local market using the same amount of fuel, enables a better utilization of non-renewable resources, and in turn enables further development of the country, which is currently limited by its energy supply.

Red Flags

  • Verified ERs (1,144,395) are materially lower than claimed ERs (1,202,884), indicating over-claiming risk or conservative verification adjustments.
  • Leakage is described as quantified, but the actual leakage deduction percentage is not found in the extracted record.
  • Crediting period dates conflict between the monitoring report (2017–2027) and the PDD (2016–2025), creating uncertainty about the applicable crediting timeline.
  • Safeguards and grievance mechanism are reported in the monitoring report but were not stated in the validation report, suggesting inconsistent social risk documentation over time.

Credit Vintages

Issued Retired Available
2017
230,569 13,105 217,464
2018
251,642 8,673 242,969
2019
253,727 23,545 230,182
2020
145,388 3,571 141,817
2021
229,559 2,369 227,190
Total 1,110,885 51,263 1,059,622

Cosa migliorerebbe questo punteggio

  • Disclose the quantified leakage deduction (percentage and calculation) and show how it was applied to arrive at verified ERs.
  • Clarify the applicable crediting period and document any renewal/revision between the PDD and later monitoring/issuance records, including baseline reassessment timing.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project; no reversals reported

Leakage

Quantified but deduction not shown

Baseline

Project-specific baseline; reassessment timing unclear

Safeguards

Mentioned later; inconsistent across documents

Double-claim

Not CORSIA-eligible

Where to buy

Marketplaces

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-02 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti