Yenikent Landfill Gas to Electricity Project
#144of 189 in Methane#39of 75 in TR#78of 154 in Intl. Carbon Registry (ICR)#125of 159 in ACM0001
Audit Analysis
The Yenikent Landfill Gas to Electricity Project uses a well-established methodology (ACM0001 v19.0) and reports no reversal events or material findings, but the available record consists solely of a PDD with no verification or monitoring reports. Key integrity elements—VVB confirmation of additionality, buffer pool allocation, and a quantified leakage assessment—are absent from the extracted data, limiting confidence in the project's robustness.
Red Flags
- No verification report or monitoring report is available; the entire record rests on a single PDD document type
- VVB name is not stated in any available document, so independent verification of additionality and baseline cannot be confirmed
- Leakage deduction is 0% with only a 'deemed negligible' justification and no quantified assessment
- Contradiction between two PDD versions (2025-03-25 and 2025-04-10) on whether benefit sharing is described
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2020 | 9,029 | 0 | 9,029 | |
| 2021 | 19,535 | 0 | 19,535 | |
| 2022 | 53,667 | 0 | 53,667 | |
| 2023 | 76,025 | 0 | 76,025 | |
| 2024 | 79,924 | 0 | 79,924 | |
| 2025 | 83,683 | 0 | 83,683 | |
| 2026 | 87,324 | 0 | 87,324 | |
| 2027 | 90,586 | 0 | 90,586 | |
| 2028 | 94,302 | 0 | 94,302 | |
| 2029 | 97,641 | 0 | 97,641 | |
| 2030 | 40,721 | 0 | 40,721 | |
| Total | 732,437 | 0 | 732,437 |
Risk Indicators
Combined test in PDD; VVB confirmation not in record
No reversals
0% deduction; 'deemed negligible' only
Project-specific, modeled; reassessment timing not stated
FPIC conducted; grievance mechanism present
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →