1.5 MW Grid connected Wind Electricity Generation at Tirunelveli District, Tamil Nadu, India.

CDM-3981 ↗

#448of 975 in India#630of 1459 in CDM (UNFCCC)#291of 806 in AMS-I.D

5.2/ 10
Integrity
6.5
Transparency
3.5
Claim Safety
6.0
Documentation
3.5

Audit Analysis

A 1.5 MW grid-connected wind project under CDM with a well-demonstrated investment additionality (IRR 8.49% vs. 14.31% benchmark) confirmed by Bureau Veritas, and a standard jurisdictional grid baseline. However, the available record is heavily skewed toward the 2010 validation report, with no monitoring data, no verified ERR, and low extraction confidence, leaving significant gaps in transparency and documentation. The project's crediting period expired in October 2020.

Red Flags

  • No monitoring reports or verified ERR figures found in the extracted record; the 33,210 tCO2e claimed figure cannot be independently cross-checked against verified data.
  • Low extraction confidence across the document set, meaning key fields (monitoring period, FNRB, usage rates, CORSIA/CCP status) are absent rather than confirmed as zero.
  • 27 Corrective Action Requests were raised during validation — a high number that, while all closed, suggests the initial PDD required substantial revision before approval.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed investment test, IRR below benchmark

Permanence

Avoidance project, no reversal risk or events

Leakage

0% deduction, minor contradiction in justification

Baseline

Jurisdictional grid EF, standard for CDM wind

Safeguards

Safeguards and benefit sharing mentioned, FPIC/grievance not stated

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01AMS ID

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents