25.3MW WHR Project of Zhejiang Leomax Group

CDM-1874 ↗

5.2 / 10
Integrity
6.1
Transparency
4.8
Claim Safety
5.0
Documentation
4.2

Score Breakdown

Integrity

verified Additionality was confirmed by the VVB, and the validation report used a combined test rather than relying on a single weak screen.

missing The verification findings include multiple corrective actions and a documented mismatch between the registered PDD and the installed turbine/generator specifications.

Transparency

verified The project has named documents from validation, monitoring, and the PDD, with SGS United Kingdom Ltd identified as the VVB.

missing Key MRV details are missing from the extracted record, including verified emission reductions, usage monitoring method, and any reassessment of the baseline.

Claim Safety

verified The validation report says leakage was deemed negligible and applies a zero leakage deduction.

missing The project is marked CORSIA-eligible, while CCP status is not stated, so the claim environment is not fully closed off.

Documentation

verified Fourteen documents were used and the extraction confidence is medium rather than low.

missing The record contains many corrective actions and a date mismatch between the validation report and a later PDD reference, which reduces confidence in documentation completeness.

Detailed Analysis

Integrity

The validation report confirms additionality using a combined test and says the VVB verified it, which supports the project’s core eligibility case. Leakage was treated as negligible with a zero deduction, but the verification findings also list many corrective actions and state that the implemented activity does not conform to the registered PDD in several equipment details, which weakens integrity confidence. No buffer pool or reversal management is stated, and reversal events are marked as not addressed, so permanence is not fully evidenced.

Transparency

The extracted record identifies SGS United Kingdom Ltd as the VVB and includes validation, monitoring, and PDD documents, which is a positive sign for traceability. At the same time, key monitoring fields are missing or not stated in available documents, including verified emission reductions, usage monitoring method, and any baseline reassessment. The monitoring period is provided, but the overall MRV picture remains incomplete in the extracted record.

Claim Safety

Claim safety is mixed because the project has a standard CDM methodology and a stated negligible leakage treatment, but the record does not provide the underlying monitoring detail needed to fully test over-crediting risk. The project is marked CORSIA-eligible, while CCP status is not stated, so the claim environment is not fully resolved. The contradiction on leakage treatment between the validation report and the later PDD also adds some reliability risk.

Documentation

Documentation quality is moderate rather than strong: fourteen documents were used and extraction confidence is medium, which avoids the lowest tier but still leaves some readability risk. The record includes several safeguards signals such as FPIC, a grievance mechanism, and benefit sharing, but it also contains multiple corrective actions and a documented mismatch between the registered PDD and onsite equipment. The crediting period is not stated, so recency and full project timeline clarity are limited.

Overall

The project scores in the middle range because it has real strengths, especially VVB-confirmed additionality and a documented leakage treatment, but those are offset by documentation inconsistencies and multiple corrective actions. I privileged the validation report over the later PDD where they conflict on additionality test type and leakage treatment because the validation report is the higher-priority independent assessment and is earlier in the project approval chain; however, the contradiction still lowers reliability. The mismatch between the registered PDD and installed equipment is the most important quality concern, and the absence of several MRV details prevents a higher transparency or claim-safety score.

Audit Analysis

This CDM waste-heat recovery project has some positive integrity signals, including VVB-confirmed additionality and a stated negligible leakage treatment. However, the record also shows multiple corrective actions and a material mismatch between the registered PDD and the installed equipment, which weakens confidence in the project documentation and implementation consistency. Public-facing MRV detail is limited in the extracted record, and the project is marked CORSIA-eligible while CCP status is not stated, leaving some claim-risk uncertainty.

Project Description

Status: Registered Type: PA Methodology: AM24 Project type: EE own generation Sub-type: Cement heat Region: Asia & Pacific Sub-region: East Asia Reductions 1st period: 162.203 ktCO2e/yr

Red Flags

  • The verification report lists multiple corrective actions and notes that the implemented project does not conform to the registered PDD in several equipment details.
  • Leakage is described as negligible in the validation report, but the PDD later appears to leave leakage unaddressed, creating a documentation inconsistency.

Credit Vintages

Issued Retired Available
2010
117,927 0 117,927
2012
171,748 0 171,748
Total 289,675 0 289,675

Cosa migliorerebbe questo punteggio

  • Provide a complete monitoring package with verified emission reductions, usage monitoring method, and any baseline reassessment clearly documented.
  • Resolve the PDD-versus-implementation discrepancies and publish a clear explanation of the corrective actions and their impact on credited emissions.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

No buffer or reversal treatment stated

Leakage

Zero deduction with negligible justification

Baseline

Project baseline, reassessment not stated

Safeguards

FPIC and grievance mechanism documented

Double-claim

CORSIA-eligible; CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-13 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti