Skip to main content
CDMWindIndiaAMS-I.D

6.55 MW Renewable energy generation project, India

CDM-10101 ↗

#535of 1935 in Renewable energy#269of 975 in India#352of 1459 in CDM (UNFCCC)#190of 806 in AMS-I.D

5.7/ 10
Integrity
5.5
Transparency
5.5
Claim Safety
5.5
Documentation
7.0

Audit Analysis

A grid-connected wind energy project in India using a jurisdictional baseline and investment-test additionality, verified by RINA Services. A material finding led to a 64% capacity reduction (6.55 MW to 2.35 MW) due to additionality failures on the NMPL component, and a ~10% discrepancy exists between two monitoring reports on total ERR. The remaining project is methodologically sound but carries notable data-reliability concerns.

Red Flags

  • Material finding: 4.2 MW (2 × 2.1 MW NMPL turbines) was withdrawn during validation because the project proponent could not demonstrate prior consideration of CDM, reducing effective capacity from 6.55 MW to 2.35 MW — yet the project name still references 6.55 MW.
  • Total ERR discrepancy of ~10% between two monitoring reports (16,719 tCO₂e in the January 2022 report vs. 18,558 tCO₂e in the October 2021 report), with no explanation provided in the extracted record.
  • Verified ERR figure is not stated in any available document, preventing independent cross-check of the claimed 16,719 tCO₂e.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-verified investment test, but 64% of capacity failed add

Permanence

Grid-connected wind; no reversal risk; no reversal events re

Leakage

0% deduction, deemed negligible — appropriate for grid-conne

Baseline

Jurisdictional baseline, grid EF 0.9528 (2012), standard for

Safeguards

Safeguards and benefit-sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25AMS-I.D. Grid connected renewable electricity generation

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents