Audit Analysis
This ACR Advanced Refrigeration project (three US retail locations) has VVB-confirmed additionality and a recent monitoring cycle, but the verification process surfaced 11 material findings spanning calculation errors, missing documentation, and cross-document inconsistencies. All findings were corrected, yet the initial quality of the project documentation and the contradiction on leakage treatment between the monitoring report and validation report raise meaningful concerns about the robustness of the credit claim.
Red Flags
- Eleven material findings were identified during verification, including refrigerant charge values in calculations that did not match Initial Charge Letters for ShopRite and Wegmans, and inconsistencies in emissions and ER figures across the GHG Project Plan, ER calculations, and Monitoring Report.
- The monitoring report (April 2025) states leakage is deemed negligible, while the validation report (May 2025) does not address leakage at all — a direct contradiction between the two most recent documents.
- The verified ERR of 15,664 equals the full lifetime ex-ante estimate, meaning 100% of lifetime credits were issued in the first ~10-month monitoring period (1,200% of the pro-rata expectation for that elapsed period). While plausible for a refrigeration project where credits are generated at installation, this warrants scrutiny of whether all three locations were genuinely operational and charged within that window.
- FPIC was not conducted and no grievance mechanism is documented, despite safeguards being mentioned in the project documents.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2024 | 14,210 | 14,210 | 0 | |
| 2025 | 1,454 | 167 | 1,287 | |
| Total | 15,664 | 14,377 | 1,287 |
Risk Indicators
VVB-confirmed combined test
Technology-based; no carbon-stock reversal risk
Deemed negligible but contradicted across documents
Project-specific; no reassessment date stated
Mentioned but FPIC not conducted; no grievance mechanism
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →