Bangna Starch Wastewater Treatment and Biogas Utilization Project (300084) (GS565 CER to VER conversion)
Score Breakdown
Integrity
verified Additionality was confirmed by the VVB through an investment test in the verification report.
missing The verification report records ten corrective actions and three clarifications, and leakage treatment is disputed between documents.
Transparency
verified The project has a named VVB, RINA Services SpA, and a defined monitoring period in the verification report.
missing Claimed versus verified issuance cannot be compared because the claimed amount is not found in the extracted record, and several key monitoring details are not stated.
Claim Safety
verified The project uses an established CDM methodology, AMS-III.H, and the verification report confirms additionality.
missing Leakage justification is inconsistent across the monitoring and verification reports, and the project is marked CORSIA-eligible with no CCP status stated.
Documentation
verified Four evidence documents were used, and extraction confidence is high.
missing The verification report is burdened by many corrective actions, and the crediting period differs from the PDD, reducing documentation reliability.
Detailed Analysis
Integrity
The verification report confirms additionality through an investment test and names RINA Services SpA as the VVB, which supports the project’s core integrity case. But the same report lists ten corrective actions and three clarifications, and reversal risk is not clearly addressed because reversal events are not discussed and no buffer pool is stated. Leakage is also weakly supported because the monitoring report says it was negligible, while the verification report says it was not addressed.
Transparency
Transparency is mixed: the project has a named verifier and a clear monitoring period in the verification report, which helps traceability. However, the extracted record does not state the claimed issuance amount, several monitoring details are missing, and the project’s leakage treatment is inconsistent across documents. The absence of a stated FNRB method and usage monitoring method also limits public MRV clarity.
Claim Safety
Claim safety is constrained by the leakage contradiction and by the lack of a stated CCP status. The project is marked CORSIA-eligible, which means it is not automatically insulated from dual-claim concerns, and the record does not show any explicit exclusion from CCP-style claims. The use of AMS-III.H and VVB-confirmed additionality are positives, but they do not fully offset the uncertainty around over-crediting and claim overlap.
Documentation
Documentation breadth is decent because four official document types were used, and extraction confidence is high. Still, the verification report contains many corrective actions and clarifications, suggesting the file required substantial cleanup before approval. The crediting period also differs from the PDD, and key fields such as buffer pool coverage and several monitoring parameters are not stated in the extracted record.
Overall
The project sits in the middle range: it has a credible additionality case and some safeguard documentation, but the verification report shows significant issues that reduce confidence. I privileged the verification report over the monitoring report for leakage because it is the later and higher-assurance document, so I treated leakage as not adequately addressed despite the earlier negligible claim. I also privileged the verification report over the PDD for the crediting period because it is more recent and reflects the verified project status, but the discrepancy still lowers reliability.
Audit Analysis
This project has some positive signs, including VVB-confirmed additionality and documented safeguards such as FPIC and a grievance mechanism. However, the verification report shows many corrective actions and clarifications, leakage treatment is inconsistent across documents, and the project is marked CORSIA-eligible with no CCP status stated, which keeps claim safety moderate at best.
Project Description
Developer: South Pole Ltd Type: Biogas - Electricity Size: Small Scale Methodology: AMS-I.D. Grid connected renewable electricity generation Crediting period: 2009-11-10 → 2016-11-09 Estimated annual credits: 41701 tCO2e SDGs: Goal 13: Climate Action, Goal 12: Responsible Production and Consumption
Red Flags
- The verification report lists ten corrective actions and three clarifications, indicating material documentation and implementation issues.
- Leakage is inconsistent: the monitoring report says it was negligible, while the verification report says it was not addressed.
- The project is CORSIA-eligible, but CCP status is not stated, leaving dual-claim risk unresolved.
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 8,000 | 8,000 | 0 | |
| Total | 8,000 | 8,000 | 0 |
Cosa migliorerebbe questo punteggio
- Publish a clear reconciliation of leakage treatment and quantify any deduction using the most recent verified monitoring evidence.
- Provide a complete registry and claims-status trail, including CCP status, issuance totals, and any buffer or reversal handling.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed investment test
No buffer pool stated
Leakage treatment inconsistent
Project baseline, reassessment not stated
FPIC and grievance mechanism present
CORSIA-eligible; CCP status not stated
Where to buy
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.