BATICIM BATI ANADOLU CIMENTO SANAYII A.S. 9 MW Cement WHR Project
#35of 295 in Turkey#69of 1339 in Verra (VCS)#1of 28 in ACM0012
Audit Analysis
A 9 MW cement waste-heat-recovery project in Turkey with a VVB-confirmed investment additionality test and smart-meter monitoring, but the verification report flagged five material findings related to data-source inconsistencies and calculation errors. The project delivered approximately 98% of its pro-rata ex-ante expectation for the six-year monitoring period, indicating no material over-crediting. Key gaps include an unaddressed non-permanence risk rating, an unstated buffer pool, and a project-specific baseline that has not been formally reassessed.
Red Flags
- Five material findings in the 2023 verification report, including data-source mismatches with the PDD and a calculation sheet that did not follow the prescribed methodology, with five corrective actions still required
- Grid emission factor of 0.5267 tCO2/MWh is from 2009 and has not been updated, while the baseline is project-specific with no documented reassessment
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 5,805 | 0 | 5,805 | |
| 2014 | 27,345 | 0 | 27,345 | |
| 2015 | 26,850 | 0 | 26,850 | |
| 2016 | 17,853 | 0 | 17,853 | |
| 2017 | 26,077 | 0 | 26,077 | |
| 2018 | 26,219 | 0 | 26,219 | |
| 2019 | 18,187 | 0 | 18,187 | |
| Total | 148,336 | 0 | 148,336 |
Risk Indicators
VVB-confirmed investment test
Non-permanence risk not addressed
0% deduction, qualitative 'deemed negligible' only
Project-specific, 2009 grid EF, no reassessment documented
Grievance mechanism present; FPIC not conducted
CORSIA explicitly excluded; CCP not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →