Bintulu Combined-Cycle Project STG Unit No.9, Tanjung Kidurong, Bintulu, Sarawak
#5of 16 in Malaysia#521of 1459 in CDM (UNFCCC)#1of 8 in ACM0007
Audit Analysis
A CDM energy-efficiency (supply-side) project in Sarawak, Malaysia, verified by LRQA with a combined additionality test confirmed. The project delivered roughly 90% of its pro-rata expected reductions for the monitored six-month period, but the record is marred by a baseline-method contradiction between the PDD and monitoring report, multiple faulty meter events requiring estimated data, and several null fields that limit full assessment.
Red Flags
- Baseline method is stated as 'project' in the monitoring report but 'jurisdictional' in the PDD — an unresolved contradiction that undermines confidence in the baseline calculation.
- Multiple gas-flow-meter failures (GT7, GT8) forced the project to use estimated fuel consumption for periods spanning May–June 2010 and December 2010, introducing measurement uncertainty into the verified ERR.
- The grid emission factor of 0.851 tCO₂e/MWh is anchored to 2007 data; no evidence of an updated or reassessed baseline was found in the extracted record.
- Five CARs and six CLs were raised during validation, including missing barrier lists and unclear alternative-scenario geography, indicating the PDD required substantial correction before registration.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 390,909 | 0 | 390,909 | |
| 2012 | 583,259 | 0 | 583,259 | |
| 2013 | 351,887 | 0 | 351,887 | |
| Total | 1,326,055 | 0 | 1,326,055 |
Risk Indicators
Combined test, VVB-confirmed
EE supply-side, no reversal risk
0% deduction, deemed negligible but not quantified in valida
Method contradiction (project vs jurisdictional), 2007 grid
Safeguards mentioned, benefit-sharing described, but FPIC an
CORSIA and CCP status not stated in extracted record
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →