Biogas recovery and CHP production in modules 1 & 2 of West Tehran Wastewater Treatment Plant
#92of 268 in Biogas#3of 5 in Iran#811of 1459 in CDM (UNFCCC)#33of 115 in AMS-I.C
Audit Analysis
A CDM biogas-recovery and CHP project at the West Tehran Wastewater Treatment Plant with VVB-confirmed additionality via an investment test, but a project-specific modeled baseline, a 0% leakage deduction justified only as 'deemed negligible' (contradicted by an appendix suggesting quantification), and a validation report that flagged 16 material findings (8 CLs, 8 CARs) before resolution. No monitoring-period data, FNRB method, or usage-rate figures were found in the extracted record, limiting the ability to verify actual delivery against the ex-ante estimate of 72,677 tCO₂e.
Red Flags
- Validation report (Jan 2017) recorded 8 compliance-level findings and 8 corrective-action requests covering baseline identification, investment-analysis inputs, monitoring locations, and UNFCCC incompleteness — a high volume of issues for a single validation cycle
- Leakage justification is contradictory: the validation report states 'deemed negligible' while an appendix (5 days earlier) indicates the leakage was 'quantified'; the 0% deduction rests on the weaker justification
- No monitoring-period data, FNRB method, or usage-rate figures were found in any extracted document, so actual credit delivery cannot be independently verified against the 72,677 tCO₂e ex-ante estimate
- Baseline is project-specific and modeled rather than jurisdictional or standardised, increasing sensitivity to input assumptions
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test; capture not legally required
no reversal e
0% deduction, 'deemed negligible' contradicted by appendix s
Project-specific modeled baseline; reassessment not yet due
Safeguards mentioned and benefit-sharing described, but FPIC
CORSIA eligibility and CCP status not stated in available do
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →