Biogas y Energía - Methane recovery & power generation from oil mill plant effluents
#16of 268 in Biogas#2of 20 in Honduras#309of 1459 in CDM (UNFCCC)#4of 55 in AMS-III.H
Audit Analysis
A CDM biogas and power-generation project in Honduras with VVB-confirmed additionality and a full-crediting-period monitoring window, but weakened by a project-specific baseline, contradictory leakage justifications across documents, and several missing operational data points (verified ERR, FNRB, usage monitoring). The project is functional but carries moderate data-reliability risk.
Red Flags
- Leakage justification is contradictory: the monitoring report (Feb 2011) describes it as 'quantified' while the validation report (Mar 2012) characterises it as 'deemed negligible', yet the deduction applied is 0% in both cases.
- Verified ERR figure is absent from the extracted record; only the ex-ante lifetime estimate of 343,473 tCO2e (validation report) and an unattributed appendix figure of 36,068 tCO2e are available, preventing a direct delivery check.
- Baseline is project-specific (validation report) with a mixed measured-and-modelled approach, and no baseline reassessment date is recorded in any document.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed barrier test
mixed evidence / unresolved risk
0% deduction, contradictory justification
Project-specific, mixed measured/modelled
Mentioned but FPIC and grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →