Bundled Renewable Power Project by Jai Bharat Gp (EKIESL-CDM.April16-02)

CDM-10364 ↗

#186of 975 in India#221of 1459 in CDM (UNFCCC)#129of 806 in AMS-I.D

6.0/ 10
Integrity
6.5
Transparency
5.5
Claim Safety
5.0
Documentation
7.0

Audit Analysis

A CDM wind project in India using the standard AMS-I.D methodology with a jurisdictional grid baseline and VVB-confirmed investment additionality. The project is fundamentally sound in design, but a significant discrepancy between the ex-ante ERR estimate in the validation report (12,940 tCO₂e) and the figure reported in the monitoring report (54,662 tCO₂e) raises data-reliability concerns, and the grid emission factor dates from 2014. All nine corrective actions from the verification process were resolved, and no outstanding findings remain.

Red Flags

  • ERR contradiction: the validation report (2017) states a total claimed ERR of 12,940 tCO₂e while the monitoring report (2021) reports 54,662 tCO₂e — a 4.2× difference that is not explained in the available documents
  • Grid emission factor of 0.977 tCO₂/MWh is from 2014 and has not been updated in the extracted record
  • Total verified ERs for the monitoring period (2017–2020) are not found in the available documents, preventing an over- or under-delivery check

Credit Vintages

IssuedRetiredAvailable
2022
54,056054,056
Total54,056054,056

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal risk

Leakage

0% deemed negligible, appropriate for wind

Baseline

Jurisdictional grid EF from 2014, not updated

Safeguards

Safeguards and benefit sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-26AMS-I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents