Audit Analysis
A CDM wind project in Tamil Nadu, India, with a well-verified investment additionality test and an appropriate jurisdictional grid baseline. However, the available record contains no monitoring or verification data, the extraction confidence is low, and two contradictions between the validation report and an earlier appendix remain, limiting confidence in the project's ongoing performance and data reliability.
Red Flags
- No verification report or monitoring report data found in the extracted record — total verified ERR and monitoring period are entirely absent
- Low extraction confidence indicates at least one key document was poorly readable, undermining reliability of the extracted facts
- Contradiction on leakage treatment: the validation report (2012) states leakage is deemed negligible, while an earlier appendix (2010) references a quantified approach — the basis for the 0% deduction is ambiguous
- Grid emission factor is fixed at the 2010 value (0.94505 tCO2/MWh) for the entire 2012–2022 crediting period with no reassessment data available
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Wind avoidance – minimal reversal risk
0% deduction, justification contradicted in appendix
Jurisdictional grid EF, standard for wind
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →