Catalytic N2O destruction project in the tail gas of the Nitric Acid Plant of Abu Qir Fertilizer Co.

CDM-0490 ↗

#46of 189 in Methane#5of 9 in Egypt#662of 1459 in CDM (UNFCCC)#4of 6 in ACM0019

5.2/ 10
Integrity
5.5
Transparency
5.0
Claim Safety
5.0
Documentation
5.5

Audit Analysis

A CDM N2O catalytic destruction project in Egypt with a barrier-test additionality assessment and a project-specific modeled baseline. The monitoring report documents multiple instrument failures and a delayed annual surveillance test, triggering corrective recalculation actions, but the project delivered roughly 105% of its pro-rata ex-ante expectation for the 2021 period. Key MRV and eligibility fields remain unconfirmed in the available record.

Red Flags

  • Multiple material findings in the 2021 monitoring period: element failures of TE-21015 and TE-21021, a wrong transmitter connection (TT-218004), and a delayed annual surveillance test due to COVID-19, all requiring recalculation of emission reductions.
  • The verified ERR figure for the monitoring period is not stated in the extracted record, leaving the final verified number unconfirmed.
  • CORSIA eligibility and CCP status are both not stated, leaving dual-channel risk unassessed.

Credit Vintages

IssuedRetiredAvailable
2007
1,223,92101,223,921
2008
1,144,91201,144,912
2009
1,932,32701,932,327
2010
409,4430409,443
2011
2,588,24502,588,245
2012
1,476,97001,476,970
2013
1,053,91401,053,914
2014
452,6340452,634
2015
1,132,80201,132,802
2016
1,069,41401,069,414
2017
316,8930316,893
2018
3,155,43103,155,431
2019
1,198,54401,198,544
2020
1,558,19601,558,196
2021
1,002,32001,002,320
Total19,715,966019,715,966

Risk Indicators

Additionality

Barrier test present; VVB sign-off not confirmed in record

Permanence

mixed evidence / unresolved risk

Leakage

Deemed negligible; justified for in-situ catalytic destructi

Baseline

Project-specific modeled baseline; no reassessment date stat

Safeguards

Safeguards and benefit sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status both not stated; dual-channel risk una

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-27ACM0019

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents