Cerro Patacón Landfill Gas Usage
#80of 189 in Methane#4of 11 in Panama#55of 99 in CerCarbono (CC)#75of 159 in ACM0001
Audit Analysis
The Cerro Patacón landfill gas project in Panama has VVB-confirmed additionality and a conservative delivery profile (approximately 78% of pro-rata ex-ante expectation), but is undermined by an extensive list of material findings including monitoring deviations, PDD formula and capacity errors, and a 0% leakage deduction that the monitoring report itself states will not be monitored. The project relies on a project-specific modeled baseline and a methodological deviation for quantification, which together limit confidence in the integrity of the credit claims.
Red Flags
- Monitoring report explicitly states leakage will not be monitored, yet the verification report classifies the 0% leakage deduction as 'quantified' — an internal inconsistency that weakens the leakage treatment
- Continuous gas volume and methane fraction monitoring was not performed; quantification relied on a methodological deviation using net electricity generation, with corrective action to install proper equipment only estimated for end of 2022
- PDD contained multiple formula errors (FCH4,PJ,y calculation), incorrect installed capacity (7.2 MW vs. verified 8.151 MW), and waste composition data inconsistent with the 2013 site study — all flagged as material findings by the VVB
- Calibration delays for energy meters were identified across 2017–2018 and 2018–2020, and calibration certificates for monitoring equipment (other than the energy meter) were not presented
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2017 | 45,637 | 2,015 | 43,622 | |
| 2018 | 85,421 | 330 | 85,091 | |
| 2019 | 104,291 | 3,468 | 100,823 | |
| 2020 | 156,980 | 17,716 | 139,264 | |
| 2021 | 125,908 | 5,090 | 120,818 | |
| Total | 518,237 | 28,619 | 489,618 |
Risk Indicators
VVB-confirmed combined test; capture not legally required
mixed evidence / unresolved risk
0% deduction called 'quantified' but monitoring report says leakage will not be monitored
Project-specific modeled baseline; reassessment timing not stated
FPIC conducted and safeguards mentioned in validation report, but grievance mechanism not stated
CORSIA eligibility and CCP status both not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →