CGN Qinghai Xitieshan Phase II 30MWp Grid-connected Solar PV Power Generation Project
#1007of 1935 in Renewable energy#550of 1084 in China#738of 1459 in CDM (UNFCCC)#792of 1287 in ACM0002
Audit Analysis
A 30 MWp grid-connected solar PV project in Qinghai, China, validated under CDM methodology ACM0002 v19.0 with a jurisdictional grid-emission-factor baseline. Additionality was confirmed by the VVB (CTC) and no material findings or corrective actions were reported, but the additionality test type is not specified in the extracted record. A notable discrepancy exists between the PDD's lifetime ERR estimate (270,998 tCO₂e) and the validation report's figure (38,714 tCO₂e), which appears to reflect a per-year versus full-crediting-period basis, and no monitoring reports are available to verify actual delivery.
Red Flags
- ERR figures differ by a factor of ~7 between the PDD (270,998) and the validation report (38,714); while the ratio matches the 7-year crediting period, the inconsistency in how 'total' is defined across documents undermines data reliability
- No monitoring reports are present in the extracted record, so actual generation and emission reductions for any elapsed period cannot be verified
- Additionality test type (investment, regulatory, or barrier) is not stated in any available document despite VVB confirmation
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed but test type unspecified
Avoidance project, no reversal risk
0% justified as negligible for grid-connected PV
Jurisdictional grid-EF baseline, 2017 value
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →