Grid emission factor: the methodology sets rules for it (ACM0002 v22 §2, p. 9). CarbonMeld reads it in the project's documents. CM-F-ACM0002-GRID-EF
ACM0002 — Grid-connected electricity generation from renewable sources
About this methodology
Projects generate renewable electricity for the grid by building or upgrading power plants. The method compares emissions from the project with the electricity generation it displaces.
- Issued by
- CDM (UNFCCC) · issuer's site
- Version
- 22.0 · source ·
- Status
- Active at CDM / UNFCCC · source ·
- Climate outcome
- Emission reductions
- Activity
- Electricity
- Official page
- cdm.unfccc.int ·
- Also used by projects of
- Verra (VCS) (745 projects)
- Global Carbon Council (GCC) (537 projects)
- Gold Standard (GS) (500 projects)
7 more
- International Carbon Registry (ICR) (77 projects)
- Universal Carbon Registry (UCR) (59 projects)
- CerCarbono (CC) (32 projects)
- BioCarbon Registry (BCR) (6 projects)
- American Carbon Registry (ACR) (3 projects)
- ITMO Registry (ITMO) (2 projects)
- Global Carbon Registry (GCR) (1 project)
How methodology v3 reads projects of this type
What CarbonMeld reads
- shown
A confirmed investment analysis A-INVEST
The documents show a project-level additionality test, the validation confirmed it, and it is an investment analysis (a numeric test of the project's finances with and without carbon revenue).
Deductions that can apply
No additionality test in the documents (renewable energy) A-TEST-NOT-STATED
Renewable energy, power generation and supply: the documents read state no additionality test. A test that the documents do not name is a different case. It takes no points. CarbonMeld applies this rule only where a check of the documents has confirmed its condition; without that check, the rule takes no points.
Set by the methodology or the programme, not assessed by our current method
- not assessed
Social safeguards and consent of communities (FPIC): any such rules come from the programme, not the methodology. Our current method does not assess it. CM-F-ACM0002-SAFEGUARDS-FPIC
Not applicable to this type — never a gap in our current method
The criterion does not apply to this methodology. Our current method never counts it as a gap.
- CM-N-LEAKAGELeakage
- CM-N-BUFFERBuffer pool
- CM-N-PERMANENCE-REVERSALPermanence and reversals
- CM-N-FNRBFraction of non-renewable biomass (fNRB)
- CM-N-USAGEUsage rate of the devices
- CM-N-REGULATORY-SURPLUSNo legal requirement for the activity
- CM-N-DURABILITY-MEASUREMENTDurability of the storage
- CM-N-FEEDSTOCK-SUSTAINABILITYSustainability of the feedstock
- CM-N-END-USE-TRACKINGTracking of the end use
The general rules apply as well. Read the general rules.
The rules of methodology v2.2, as they were: the archived v2.2 page.
History and transitions
Its revision: VMR0017
Grid-connected electricity generation from renewable sources (ACM0002 Revision)
Replaces AM0005
AM0005 | Small grid-connected zero-emissions renewable electricity generation --- Version 1.0 | ACM0002 | EB 23
All 25 versions · current v22.0
-
v22.0adopted 31 May 2024currentsource
Broaden the applicability of the methodology to cover Greenfield pumped hydro storage projects operating in coordination with Greenfield renewable energy plant.
-
v21.0adopted 2 Nov 2022source
Broaden the applicability of the methodology to cover the integration of battery energy storage systems.
-
v20.0adopted 28 Nov 2019source
Remove the positive list and introduce reference to TOOL32 (as the positive list was moved to TOOL32).
-
v19.0adopted 31 Aug 2018source
Extend the validity of the positive list.
-
v18.1adopted 23 May 2018source
Editorial revision to correct cross-reference of equation numbers in paragraph 41 (b).
-
v18.0adopted 26 Apr 2018source
Extend the validity of the positive list.
-
v17.0adopted 13 May 2016source
Include the provision for geothermal technologies with binary or closed loop heat exchange systems.
-
v16.0adopted 20 Nov 2014source
Standardize the requirements on additionality in the methodology by including a positive list of technologies.
-
v15.0adopted 1 Jun 2014source
Expand the applicability of the methodology to cover projects involving construction of a new reservoir together with new power plant(s)/unit(s) for increased power generation in integrated hydro power projects; Include the definition of …
-
v14.0adopted 4 Oct 2013source
Remove requirements for specific case CPA-DDs and frequency of updating of eligibility criteria as these requirements are specified in the relevant standards Change the title from “ACM0002: Consolidated baseline methodology for …
-
v13.0.0adopted 11 May 2012source
Provide more clarity on how the quantity of net electricity generation supplied by the project plant/unit to the grid shall be monitored; Introduce provisions for the use of this methodology in a project activity under a PoA.
-
v12.2.0adopted 25 Nov 2011source
The amendment incorporates applicability conditions on how the methodology shall be applied in cases where the project activity includes hydropower plant(s) with multiple reservoirs.
-
v12.1.0adopted 26 Nov 2010source
Includes a definition for reservoir.
-
v12.0.0adopted 17 Sept 2010source
Includes a definition for existing reservoir.
-
v11adopted 12 Feb 2010source
-
v10adopted 28 May 2009source
Expands the applicability of the methodology to project activities that retrofit or replace renewable energy power generation units, to restore the installed power generation capacity to or above its original level. This revision includes …
-
v09adopted 13 Feb 2009source
Inclusion of project emissions for operation of solar power plant and backup power generation of all the renewable energy plants.
-
v08adopted 28 Nov 2008source
Incorporate changes in equation 9 of baseline emissions to account for the cases where the expansion of existing capacity of plant takes place as an additional energy generation unit is installed under CDM project activity.
-
v07adopted 30 Nov 2007source
General editorial revision of the methodology to put it in the new format; Inclusion of the TOOL07; Inclusion of the TOOL03; Inclusion of the definitions for power plant/unit, installed power generation capacity, electricity capacity …
-
v06adopted 12 May 2006source
Revision of the applicability conditions to include hydro power plants with new reservoirs that have power density greater than 4 W/m2 and inclusion of the equation to calculate the emissions from the reservoir in the emissions reductions …
-
v05adopted 24 Feb 2006source
Inclusion of guidances in the baseline section stating that power plant capacity additions registered as CDM project activities should be excluded from the calculation of emission factors and that if 20 per cent falls on partial capacity …
-
v04adopted 25 Nov 2005source
Inclusion of a procedure in the project boundary section on how to deal with cases where the application of the methodology does not result in a clear grid boundary.
-
v03adopted 30 Sept 2005source
Revision of the baseline section in order to include project activities that modify or retrofit an existing electricity generation facility and the corresponding procedure to determine the baseline scenario in this case (EGbaseline).
-
v02adopted 3 Dec 2004source
Inclusion of the following paragraph in the Baseline section as per request by the Board: “Which of the plausible alternatives scenarios, as listed in step 1 of the additionality text, is the most likely baseline scenario? Please provide …
-
v01adopted 3 Sept 2004source
Initial adoption.
Top projects using ACM0002
This page ranks projects using ACM0002 by their CarbonMeld document-based ratings. The rank compares project ratings; it is not a rating of the methodology itself.
984 rated projects of the 6,005 tracked in this methodology · average rating 3.3/10 · ranked by CarbonMeld's document-based rating: additionality, quantification, permanence (where carbon is stored) and claim safety. Showing the top 50.
3,275 analysed project pages, A–Z →
Which registries list projects under ACM0002?
In CarbonMeld's data, ACM0002 projects are on 11 registries: CDM (4,043), Verra (745) and Global Carbon Council (537), and 8 more. Being listed on a registry is not the same as being registered: the «Registered» column counts the projects each registry shows as registered, and credits are issued only after each verification.
| Registry | Projects | Registered | Projects list |
|---|---|---|---|
| CDM (UNFCCC) | 4,043 | 3,244 | See the list |
| Verra (VCS) | 745 | 417 | See the list |
| Global Carbon Council (GCC) | 537 | 171 | See the list |
| Gold Standard (GS) | 500 | 434 | See the list |
| International Carbon Registry (ICR) | 77 | 32 | See the list |
| Universal Carbon Registry (UCR) | 59 | 40 | See the list |
| CerCarbono (CC) | 32 | 17 | See the list |
| BioCarbon Registry (BCR) | 6 | 5 | See the list |
| American Carbon Registry (ACR) | 3 | 0 | See the list |
| ITMO Registry (ITMO) | 2 | 0 | See the list |
| Global Carbon Registry (GCR) | 1 | 0 | See the list |
Counts of project records in CarbonMeld's data, with or without a CarbonMeld analysis, so they can be larger than the ranking below. «Registered» counts the records whose current registry status is «registered», as last read (25 November 2026); projects in a later status, such as awaiting verification approval, late to verify or completed, are not in that column.
- 4 4.2
- 5 4.2
- 6 4.2
- 7 4.2
- 8 4.2
- 9 4.2
- 10 4.2
- 11 4.2
- 12 4.1
- 13 4.1
- 14 4.1
- 15 4.1
- 16 4
- 17 4
- 18 4
- 19 4
- 20 4
- 21 4
- 22 4
- 23 4
- 24 4
- 25 4
- 26 4
- 27 4
- 28 4
- 29 4
- 30 4
- 31 4
- 32 4
- 33 4
- 34 4
- 35 4
- 36 4
- 37 4
- 38 4
- 39 4
- 40 4
- 41 4
- 42 4
- 43 4
- 44 4
- 45 4
- 46 4
- 47 4
- 48 4
- 49 4
- 50 4