The Akıncı Hydroelectric Power Plant is a registered VCS renewable-energy project with a VVB-confirmed investment additionality test and a jurisdictional baseline, but it carries a heavy burden of 13 material findings and 13 corrective actions, including a critical error in which emission reductions were initially calculated on gross generation rather than net electricity exported and a roughly 477-fold discrepancy in reported reservoir area. The absence of a buffer pool, unaddressed reversal risk, an outdated 2012 grid emission factor, and the lack of any stated CORSIA or CCP status collectively limit confidence in the integrity and safety of the claimed credits.

Red Flags

  • Emission reductions were initially calculated using gross generation instead of net electricity exported, creating a material over-crediting risk (2024 verification report).
  • Reservoir area reported as both 314.517 m² and 150,000 m² across documents — a discrepancy of roughly 477× that undermines confidence in the project's physical parameters (2024 verification report).
  • No buffer pool percentage is stated in any available document, and reversal events are listed as 'not addressed,' leaving permanence risk unquantified for a hydro asset.
  • Verra raised concerns about additionality because no credits had been issued since the project's 2014 registration, and the verification report did not confirm whether methodology deviations impact baseline, additionality, or applicability.
  • The grid emission factor of 0.514 tCO₂/MWh is drawn from 2012 data; Turkey's generation mix has shifted substantially in the intervening decade, making the baseline potentially stale.

Credit Vintages

IssuedRetiredAvailable
2018
16,4003,87412,526
2019
231,00646,059184,947
2020
223,39379,039144,354
2021
90,754090,754
2022
31,0111,76529,246
Total592,564130,737461,827

Risk Indicators

Additionality

VVB-confirmed investment test, but Verra questioned additionality due to no credit issuance since 2014

Permanence

reversal events not addressed

Leakage

0% deduction with thin 'deemed negligible' justification

Baseline

Jurisdictional baseline per 2024, but grid EF from 2012 and reassessment timing unconfirmed

Safeguards

FPIC conducted, grievance mechanism present, safeguards documented (2024 verification)

Double-claim

CORSIA and CCP statuses not stated; dual-channel risk unassessed

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents