CEMEL HYDRO BUNDLE
GS-130 ↗ · current registry ID: GS1208
#258of 295 in Turkey#1278of 1801 in Gold Standard (GS)#1083of 1287 in ACM0002
Audit Analysis
The Cemel Hydro Bundle is a small hydro avoidance project in Turkey verified by RINA, with a confirmed investment-test additionality and reasonable leakage treatment. However, a project-specific baseline built on a 2010 grid emission factor, a significant discrepancy between the PDD ex-ante estimate (36,451 tCO₂) and the monitoring-report claim (54,101 tCO₂) despite actual generation running 26 % below the ex-ante figure, and a low extraction-confidence rating across 31 documents collectively limit confidence in the credit quantity and baseline robustness.
Red Flags
- The monitoring report claims 54,101 tCO₂ while the PDD ex-ante estimate is 36,451 tCO₂, yet the verification report notes actual generation (109,763 MWh) is 26 % below the ex-ante estimate (148,103 MWh) — the higher credit claim is not supported by the generation data.
- The grid emission factor used in the baseline is from 2010 (0.4929 tCO₂/MWh); Turkey's grid mix has likely changed substantially over 15 years, potentially inflating the avoided-emissions baseline.
- Nine contradictions were identified across documents, including conflicting FPIC status (conducted per the 2021 verification report vs. not conducted per the 2024 PDD) and conflicting baseline methodology (project-specific per the verification report vs. jurisdictional per the monitoring report).
- The verification report was conducted remotely (no onsite visit), and the VVB itself flagged the need for an onsite verification in the next cycle.
- Min extraction confidence is rated low, indicating at least one key document was poorly readable, reducing reliability of the extracted data.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2015 | 15,465 | 15,465 | 0 | |
| 2016 | 38,665 | 37,874 | 791 | |
| 2017 | 41,426 | 40,976 | 450 | |
| 2018 | 24,684 | 24,655 | 29 | |
| 2019 | 24,728 | 9,493 | 15,235 | |
| 2020 | 37,355 | 747 | 36,608 | |
| 2021 | 22,537 | 281 | 22,256 | |
| 2022 | 22,088 | 0 | 22,088 | |
| 2023 | 25,921 | 0 | 25,921 | |
| 2024 | 15,795 | 0 | 15,795 | |
| Total | 268,664 | 129,491 | 139,173 |
Risk Indicators
VVB-confirmed investment test
Hydro avoidance – low reversal risk
0 % deduction, deemed negligible
Project-specific, 2010 grid EF
FPIC contradiction; grievance present
Not CORSIA-eligible; no dual registration
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →