Barroso 20MW hydroelectric project
GS-854 ↗ · current registry ID: GS4822
#359of 770 in Renewable energy#9of 18 in Colombia#250of 426 in Gold Standard (GS)#268of 383 in ACM0002
Audit Analysis
The Barroso 20 MW hydro project is a Gold Standard-registered small hydro scheme in Colombia with VVB-confirmed additionality and a 2023 baseline reassessment, but it is undermined by a project-specific baseline, an unaddressed 0% leakage deduction, a grid emission factor that was initially overstated by 33%, and an extensive list of material findings and corrective actions spanning ownership changes, meter calibration delays, and a tunnel collapse event. Verified emissions reductions for the 2021 monitoring period exceeded the pro-rata expectation by roughly 54%, partly attributable to La Niña-driven higher flows, which is a positive signal but does not offset the structural documentation and methodological gaps.
Red Flags
- Leakage deduction of 0% with justification recorded as 'not addressed' in the 2023 verification report, while the monitoring report claims it was 'deemed negligible' — an unresolved contradiction that leaves the leakage treatment unverified.
- Grid emission factor was initially reported as 0.403 tCO2e/MWh in the 2023 verification report but corrected to 0.303 per UPME Resolution 000320, meaning early-period credits were overestimated by approximately 33%.
- Twenty or more corrective action requests were raised across validation and verification cycles, including missing Ongoing Financial Need assessment, unclear ex-ante generation traceability, and a tunnel collapse event that was not initially disclosed in the monitoring report.
- Ownership changed from Barroso S.A.S E.S.P to ISAGEN S.A E.S.P during the crediting period, triggering a FAR and requiring PDD updates — a material change that could affect additionality and benefit-sharing arrangements.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2018 | 35,143 | 31,063 | 4,080 | |
| 2019 | 60,378 | 5,512 | 54,866 | |
| 2020 | 72,951 | 12,055 | 60,896 | |
| 2021 | 56,026 | 5,476 | 50,550 | |
| Total | 224,498 | 54,106 | 170,392 |
Risk Indicators
VVB-confirmed investment test
No buffer pool stated; hydro avoidance type
0% deduction, justification unaddressed
Project-specific, reassessed 2023
Grievance mechanism present; FPIC not conducted
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →