Chambal Power Limiteds (CPL) proposed 7.5 MW biomass based power project at Rangpur, Kota District, Rajasthan, India
#79of 352 in Biomass#472of 975 in India#663of 1459 in CDM (UNFCCC)#308of 806 in AMS-I.D
Audit Analysis
A 7.5 MW biomass power project under CDM with VVB-confirmed additionality and a reasonable 0% leakage deduction, but undermined by a baseline method contradiction between the validation and monitoring reports, absent feedstock sustainability evidence, and under-delivery of roughly 73% of the pro-rata expected emissions reductions in the first monitoring period. The project lacks a buffer pool, FNRB data, and usage monitoring details, leaving meaningful gaps in both integrity and transparency.
Red Flags
- Baseline method is described as 'project' in the monitoring report (2021) but 'jurisdictional' in the validation report (2020) — an unresolved contradiction that affects the credibility of the baseline calculation.
- Feedstock sustainability and carbon content testing are not stated in any available document, a critical gap for a biomass energy project.
- First monitoring period delivered only ~73% of the pro-rata expected emissions reductions (32,388 vs ~44,493 expected), suggesting potential over-crediting in the ex-ante estimate.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2007 | 20,312 | 0 | 20,312 | |
| 2008 | 15,503 | 0 | 15,503 | |
| 2009 | 46,824 | 0 | 46,824 | |
| 2010 | 27,418 | 0 | 27,418 | |
| 2011 | 43,516 | 0 | 43,516 | |
| 2012 | 19,268 | 0 | 19,268 | |
| 2013 | 20,681 | 0 | 20,681 | |
| 2014 | 19,386 | 0 | 19,386 | |
| 2016 | 90,796 | 0 | 90,796 | |
| 2021 | 223,051 | 0 | 223,051 | |
| Total | 526,755 | 0 | 526,755 |
Risk Indicators
VVB-confirmed, test type not specified
no reversals reported
0% deduction, 'deemed negligible'; minor doc inconsistency
Method contradicts between docs; grid EF 2018
Safeguards mentioned; FPIC and grievance not stated
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →