China Resources Juxian Donghong Phase I Wind Power Project
#928of 1935 in Renewable energy#488of 1084 in China#665of 1459 in CDM (UNFCCC)#723of 1287 in ACM0002
Audit Analysis
A CDM wind power project with a verified combined additionality test and jurisdictional grid baseline, but undermined by 13 material findings requiring corrective action (including IRR calculation and common-practice corrections), a significant discrepancy between the PDD and validation-report ERR figures, and low extraction confidence across the document set. The fundamental project design (wind displacing grid electricity) is low-risk, but the documentation and verification record show notable gaps.
Red Flags
- The PDD (2012-03-28) reports a total claimed ERR of 711,018 tCO2e while the validation report (2012-04-16) reports 101,574 tCO2e — a 7× discrepancy that, while likely reflecting annual vs. 7-year crediting-period totals, was not reconciled in the extracted record and creates ambiguity about the true lifetime credit volume.
- Thirteen material findings and thirteen corrective actions were raised during validation, including corrections to the IRR calculation (CAR 7), common-practice analysis capacity range (CAR 9), and emission-reduction formulas (CAR 5), indicating the initial additionality and quantification case required substantial revision before approval.
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable, reducing reliability of the structured data used for this assessment.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Physical wind infrastructure, no reversal risk
Negligible, appropriate for wind
Jurisdictional grid EF (2010)
Mentioned but FPIC and grievance mechanism not documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →