Chongqing Iron & Steel Co. Ltd. Waste Gas to Electricity Project
#489of 1084 in China#666of 1459 in CDM (UNFCCC)#15of 28 in ACM0004
Audit Analysis
A CDM waste-gas-to-electricity project with a solid combined additionality test confirmed by the VVB, but undermined by six material findings (including a corrective action on monitoring-plan compliance), a contradictory baseline method (jurisdictional vs. project-specific), a 0% leakage deduction with inconsistent justification, and conflicting ERR figures across monitoring reports. The project sits under the older CDM standard, so the absence of a buffer pool and CORSIA/CCP designations is expected, but the data-reliability issues lower confidence in the verified credits.
Red Flags
- Six material findings in the validation report, including CAR #4 requiring the project proponent to revise the monitoring plan for full compliance with the monitoring methodology
- Baseline method contradicts between documents: the validation report (2008) describes a project-specific baseline while the monitoring report (2011) refers to a jurisdictional baseline
- Two monitoring reports give materially different claimed ERR figures (212,686 in the 2010 report vs. 57,308 in the 2011 report), creating uncertainty about the true ex-ante expectation
- Leakage deduction is 0% yet the justification is inconsistent: the validation report deems leakage negligible while the monitoring report labels it 'quantified'
- Two corrective actions remain open, including a requirement to revise and improve project design documents based on expert opinions
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 35,740 | 0 | 35,740 | |
| 2010 | 83,247 | 0 | 83,247 | |
| 2011 | 212,559 | 0 | 212,559 | |
| 2012 | 57,308 | 0 | 57,308 | |
| Total | 388,854 | 0 | 388,854 |
Risk Indicators
Combined test, VVB-confirmed
no reversal data
0% deduction, inconsistent justification
Method contradicts across documents
Mentioned but not detailed
CCP/CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →