CTR Candeias Landfill Gas Project

CDM-3958 ↗

#62of 189 in Methane#91of 211 in Brazil#819of 1459 in CDM (UNFCCC)#59of 159 in ACM0001

5.0/ 10
Integrity
5.5
Transparency
5.0
Claim Safety
4.0
Documentation
5.5

Audit Analysis

The CTR Candeias Landfill Gas Project (CDM-3958) is a methodology-compliant LFG capture project with VVB-confirmed additionality, but suffers from an internal contradiction in claimed emission reductions, inconsistent leakage treatment across documents, and seven outstanding corrective actions. The project-specific modeled baseline and absence of stated permanence or safeguards detail limit confidence in the credit's robustness.

Red Flags

  • Internal contradiction in the monitoring report: total ERR claimed appears as both 163,204 and 354,934 tCO2e in the same document (2021-02-03), undermining data reliability
  • Leakage justification is inconsistent: the validation report (2020) states leakage is 'deemed negligible' while the monitoring report (2021) records it as 'not addressed', despite the methodology stating leakage is not applicable
  • Seven corrective actions remain outstanding, including updating the PDD for national policies, correcting emission factor data vintage, and providing evidence for the SPECflare parameter

Credit Vintages

IssuedRetiredAvailable
2014
104,6320104,632
2015
138,1700138,170
2016
145,3930145,393
2017
158,3860158,386
2020
297,1280297,128
2021
530,8840530,884
Total1,374,59301,374,593

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

mixed evidence / unresolved risk

Leakage

0% deduction, justification inconsistent across docs

Baseline

Project-specific modeled baseline, reassessed 2020

Safeguards

Safeguards and benefit sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-27ACM0001

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents