Duzce Aksu Hydro Electricity Power Plant
Score Breakdown
Integrity
verified The validation/verification record indicates additionality was confirmed by the VVB using a combined approach under ACM0002.
missing Baseline is project-specific and the timing of any baseline reassessment is not stated in the extracted record; leakage treatment is inconsistent across monitoring reports.
Transparency
verified A VVB is identified (Re-carbon) and the monitoring period (2022-01-01—2023-08-31) and grid emission factor (0.53323) are disclosed in the monitoring documentation.
missing The monitoring report raised multiple CARs (including inconsistent monitored parameters and missing metering QA/QC details), and key public-claim fields like CORSIA/CCP status are not stated in the extracted record.
Claim Safety
verified Claimed and verified ER match in the extracted record for the latest cycle (99,931 tCO2e), reducing immediate over-claim risk for that period.
missing Contradictory verified ER figures across validation reports and unclear CORSIA/CCP status increase greenwashing and over-crediting risk.
Documentation
verified A relatively large document set was used (19 documents including PDD, monitoring report, validation report, issuance) with high extraction confidence.
missing Numerous CARs in the 2024 monitoring report indicate documentation quality/control issues despite overall availability.
Detailed Analysis
Integrity
The validation/verification record indicates additionality was confirmed by the VVB, and the project applies ACM0002 (version 16.0.0), which supports methodological consistency. However, the baseline is described as project-specific and the timing of any baseline reassessment is not stated in the extracted record, which weakens confidence that baseline conditions remain current. Leakage is treated as a 0% deduction with a justification of “deemed negligible” in the 2024 monitoring report, but an earlier monitoring report (2020) is recorded as not addressing leakage, creating an integrity-relevant inconsistency.
Transparency
The monitoring report (2024-01-08) clearly states the monitoring period (2022-01-01—2023-08-31) and provides a grid emission factor (0.53323), and the VVB is identified as Re-carbon. Transparency is reduced by the monitoring report’s corrective action requests, including inconsistencies in monitored parameters and missing supporting details such as a meter location diagram and calibration/serial/accuracy information. CORSIA eligibility and CCP status are not stated in the extracted record, limiting registry/market transparency for downstream claims.
Claim Safety
For the latest cycle, the extracted record shows claimed and verified emission reductions are the same (99,931 tCO2e), which is a positive signal for that monitoring period. Claim safety is nonetheless weakened by a major contradiction across validation reports: one validation report (2024-02-16) shows 99,931 tCO2e verified, while an earlier validation report (2022-10-19) shows 51,842 tCO2e, raising the risk of confusion or misstatement in marketing claims. With CORSIA eligibility and CCP status not stated in the extracted record, buyers cannot easily assess eligibility-related claim boundaries.
Documentation
Documentation coverage is relatively strong: the extracted record references a PDD, monitoring report, validation report, and issuance, with 19 documents used and high extraction confidence. However, the 2024 monitoring report includes multiple CARs (e.g., inconsistent project proponent naming, missing footnote, inconsistent monitored parameters, and incomplete metering QA/QC documentation), indicating quality-control gaps in submitted documentation. The crediting period (2014-04-25—2024-04-24) and the recent monitoring period are stated, supporting recency, but baseline reassessment timing is not evidenced.
Overall
Overall scoring reflects moderate quality with notable reliability concerns driven by contradictions and CARs. On leakage, the 2024 monitoring report’s “deemed negligible” justification was privileged over the 2020 monitoring report’s “not addressed” because it is more recent and provides an explicit position, but the inconsistency still reduces confidence. On safeguards (FPIC, grievance mechanism, benefit sharing), the 2024 monitoring report was privileged over the 2016 PDD because it is more recent, yet the direct contradiction suggests safeguards may have been added or documented later, so scores are adjusted downward. For verified ERs, the 2024-02-16 validation report value (99,931) was privileged as the more recent figure and it matches the claimed ER in the extracted record, but the earlier 51,842 figure indicates a material documentation discrepancy that lowers transparency and claim-safety scores. (Gate rules note: integrity is above 4.0 and documentation is above 3.0, so no automatic caps would apply.)
Audit Analysis
This VCS hydropower project reports 99,931 tCO2e for the 2022-01-01 to 2023-08-31 monitoring period, with the same figure shown as verified in the extracted record. Integrity is moderate: additionality is VVB-confirmed, but baseline reassessment timing is not evidenced and several internal inconsistencies across documents reduce confidence. Safeguards and stakeholder provisions appear stronger in recent monitoring documentation than in the original PDD, creating a disclosure reliability concern.
Project Description
The Duzce Aksu Hydro Electric Power Plant (HEPP) generates renewable electricity by utilizing water resources to deliver power to the Turkish National Power Grid. With a total installed capacity of 46.2 MW, the project produces electricity without emitting airborne pollutants or GHG emissions, and delays the need for conventional thermal power plants to be added to the grid.
Red Flags
- Conflicting verified ER values across validation reports (99,931 vs 51,842), indicating potential reporting/issuance reliability issues.
- Multiple contradictions between the PDD (2016) and later monitoring report (2024) on FPIC, grievance mechanism, and benefit sharing, suggesting retroactive or inconsistently documented safeguards.
- Corrective Action Requests in the monitoring report include inconsistencies in monitored parameters and missing meter diagram/calibration details, weakening MRV confidence.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 32,916 | 32,916 | 0 | |
| 2015 | 61,243 | 61,243 | 0 | |
| 2016 | 53,709 | 53,709 | 0 | |
| 2017 | 49,418 | 49,418 | 0 | |
| 2018 | 42,996 | 36,856 | 6,140 | |
| 2019 | 94,713 | 3 | 94,710 | |
| 2020 | 52,527 | 14,963 | 37,564 | |
| Total | 387,522 | 249,108 | 138,414 |
Cosa migliorerebbe questo punteggio
- Publish a clear reconciliation note (or registry link) explaining the difference between the 51,842 and 99,931 verified ER figures across validation reports, including which monitoring period(s) each figure covers.
- Strengthen MRV transparency by providing complete metering documentation (line diagram, calibration certificates, serial numbers, accuracy class) and resolving parameter inconsistencies flagged in the 2024 monitoring report CARs.
- Provide consistent, auditable safeguards evidence (FPIC records, grievance procedure documentation, benefit-sharing description) and explain changes relative to the 2016 PDD.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed additionality (combined test)
Avoidance project; no reversal risk indicated
0% leakage with inconsistent treatment across reports
Project-specific baseline; reassessment timing unclear
Safeguards/FPIC reported later but contradict PDD
CORSIA/CCP status not stated in extracted record
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →