Emission reductions through partial substitution of fossil fuel with alternative fuels in the 2 cement plants of PT Holcim Indonesia Tbk
#44of 352 in Biomass#7of 33 in Indonesia#464of 1459 in CDM (UNFCCC)#2of 6 in ACM0003
Audit Analysis
A CDM biomass fuel-substitution project at two Indonesian cement plants with VVB-confirmed additionality and an established methodology (ACM0003 v04), but hampered by a project-specific baseline, a lack of verified ERR figures, and several material findings around AFGHG calculation transparency and fuel availability that required corrective action. The grid emission factor discrepancy between the PDD and monitoring report, combined with missing monitoring parameters, limits confidence in the claimed credit volume.
Red Flags
- AFGHG calculation lacked transparency regarding emission factors for alternative fuels, flagged as a material finding in the verification process
- Grid emission factor differs between the PDD (0.754, 2008) and the monitoring report (0.891, 2011), with no documented explanation for the change
- No verified ERR figure is available in the extracted record, preventing an independent check of the 125,771 tCO₂e claimed
- Leakage is described as 'quantified' but the actual deduction percentage is not stated in any available document
- Crediting period start date differs between the validation report (2008-04-01) and the monitoring report (2008-09-02)
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 12,335 | 0 | 12,335 | |
| 2012 | 124,195 | 0 | 124,195 | |
| Total | 136,530 | 0 | 136,530 |
Risk Indicators
VVB-confirmed combined test
low inherent reversal risk
Quantified but percentage not stated
Project-specific; no reassessment date
Mentioned; FPIC and grievance not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →