EUTHENIA ENERGY CENTER
#26of 61 in Biochar#2of 5 in Spain#59of 111 in Puro.earth (PUR)
Audit Analysis
The Euthenia Energy Center is a Spanish biochar project verified under the Puro standard with a named VVB (Normec Verifavia SAS) and a confirmed combined additionality test. However, critical permanence and leakage parameters are absent from the extracted record, the plant was not operational during the verification visit, and a corrective action was issued regarding tracking of biochar sold for non-eligible activities. The project shows moderate quality with notable gaps in biochar-specific risk management.
Red Flags
- The plant was not operational during the verification visit, so live observation of the biochar production process was not possible (material finding, verification report 2024-12-19).
- No buffer pool, permanence mechanism, or permanence claim period is stated in the extracted record — a significant gap for a biochar project where carbon loss through weathering or erosion is a real risk.
- No leakage deduction or leakage justification is stated, and a corrective action was issued recommending a more detailed tracking system for biochar sold for non-eligible activities, suggesting potential leakage or double-use risk.
- The project uses a project-specific baseline rather than a jurisdictional or standardised one, increasing the risk of baseline over-crediting.
- Permanence claim not stated in available documents
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2025 | 4,520 | 4,520 | 0 | |
| Total | 4,520 | 4,520 | 0 |
Risk Indicators
VVB-confirmed combined test
No buffer pool or permanence period stated
No deduction or justification; tracking gap flagged
Project-specific; no reassessment date
Mentioned but FPIC and grievance mechanism not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →