Fuhui Inner Mongolia Narenbaolige Wind Farm Project

CDM-2072 ↗

#940of 1935 in Renewable energy#496of 1084 in China#682of 1459 in CDM (UNFCCC)#737of 1287 in ACM0002

5.2/ 10
Integrity
5.5
Transparency
4.5
Claim Safety
5.5
Documentation
5.5

Audit Analysis

A CDM wind farm project with solid fundamentals — VVB-confirmed additionality, a jurisdictional baseline, and no material findings — but hampered by a significant discrepancy between the PDD and validation report on total emissions reductions (681,107 vs 97,301 tCO₂e) and several missing monitoring and permanence details. The project is inherently low-risk given the wind technology, yet the documentation gaps and ERR contradiction prevent a higher confidence rating.

Red Flags

  • The PDD (Sep 2019) reports a total ERR of 681,107 tCO₂e while the validation report (Nov 2019) confirms only 97,301 tCO₂e — a roughly 7-fold discrepancy that undermines confidence in the ex-ante estimate
  • No buffer pool percentage, reversal event history, or monitoring period is stated in the available documents, leaving permanence and MRV verification incomplete
  • FNRB method and value are not stated, making it impossible to independently verify the grid emission factor application

Credit Vintages

IssuedRetiredAvailable
2009
36,631036,631
2010
105,0780105,078
2012
90,264090,264
2014
132,5110132,511
Total364,4840364,484

Risk Indicators

Additionality

VVB-confirmed

Permanence

mixed evidence / unresolved risk

Leakage

Negligible, justified for wind

Baseline

Jurisdictional, reassessed 2019

Safeguards

Mentioned but FPIC/grievance not detailed

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-29ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents