Fuhui Inner Mongolia Narenbaolige Wind Farm Project
#940of 1935 in Renewable energy#496of 1084 in China#682of 1459 in CDM (UNFCCC)#737of 1287 in ACM0002
Audit Analysis
A CDM wind farm project with solid fundamentals — VVB-confirmed additionality, a jurisdictional baseline, and no material findings — but hampered by a significant discrepancy between the PDD and validation report on total emissions reductions (681,107 vs 97,301 tCO₂e) and several missing monitoring and permanence details. The project is inherently low-risk given the wind technology, yet the documentation gaps and ERR contradiction prevent a higher confidence rating.
Red Flags
- The PDD (Sep 2019) reports a total ERR of 681,107 tCO₂e while the validation report (Nov 2019) confirms only 97,301 tCO₂e — a roughly 7-fold discrepancy that undermines confidence in the ex-ante estimate
- No buffer pool percentage, reversal event history, or monitoring period is stated in the available documents, leaving permanence and MRV verification incomplete
- FNRB method and value are not stated, making it impossible to independently verify the grid emission factor application
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 36,631 | 0 | 36,631 | |
| 2010 | 105,078 | 0 | 105,078 | |
| 2012 | 90,264 | 0 | 90,264 | |
| 2014 | 132,511 | 0 | 132,511 | |
| Total | 364,484 | 0 | 364,484 |
Risk Indicators
VVB-confirmed
mixed evidence / unresolved risk
Negligible, justified for wind
Jurisdictional, reassessed 2019
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →