5.0/ 10
Integrity
5.5
Transparency
4.0
Claim Safety
5.5
Documentation
4.5

Audit Analysis

A small 12.9 MW run-of-river hydropower project in Gansu, China, validated under CDM methodology AMS-I.D with a jurisdictional baseline and investment-test additionality. The project is structurally sound but the extracted record lacks verification/monitoring data, a buffer pool, and several MRV details, leaving meaningful evidence gaps. No material compliance failures were identified, but the absence of post-validation monitoring data prevents confirmation of actual delivery.

Red Flags

  • No buffer pool or permanence mechanism is documented for the 7-year crediting period, leaving reversal risk unaddressed in the extracted record.
  • No verification or monitoring report data was found (total ERR verified is absent), so actual credit delivery cannot be confirmed against the 41,616 tCO₂e/yr claim.
  • The validation report lists six clarification requests (methodology number, OM/BM values, parameter naming, EGfacility correction), indicating the PDD required multiple corrections before approval.

Credit Vintages

IssuedRetiredAvailable
2011
146,8600146,860
2012
73,769073,769
2013
49,244049,244
Total269,8730269,873

Risk Indicators

Additionality

Investment test present; VVB confirmation not explicit in re

Permanence

reversal risk unaddressed

Leakage

0% deduction, 'deemed negligible' — reasonable for small hyd

Baseline

Jurisdictional grid EF (0.6266, 2013), standardised methodol

Safeguards

Safeguards and benefit-sharing mentioned; FPIC and grievance

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-29AMS-I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents