Gas Flaring Reduction at Neelam & Heera Asset
#569of 975 in India#836of 1459 in CDM (UNFCCC)
Audit Analysis
A CDM gas flaring reduction project with a VVB-confirmed combined additionality test and standard methodology (AM0009), but undermined by a material finding that the Neelam Platform compressor was non-operational throughout the entire monitoring period, a 10× discrepancy in lifetime ERR figures between the validation report and monitoring report, and a project-specific baseline. The project's operational reliability and data consistency raise meaningful concerns about the robustness of its verified reductions.
Red Flags
- Material finding: technical snags at Neelam Platform caused non-operation of the compressor during the entire monitoring period (2012-12-24 to 2013-12-31), casting doubt on whether the 20,430 tCO2e verified reductions were actually attributable to project activity
- 10× discrepancy in lifetime ERR: the validation report (Oct 2012) states 658,110 tCO2e while the monitoring report (Mar 2014) states 65,811 tCO2e — a factor-of-ten difference that suggests a possible transcription error or fundamental inconsistency in the project's quantification
- 18 Corrective Action Requests were raised and closed during verification, indicating significant documentation or methodological issues that had to be remediated before the monitoring report could be accepted
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
Negligible, appropriate for flaring
Project-specific, measured
Mentioned but FPIC/grievance not detailed
CORSIA/CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →