Grouped Commercial Electric Vehicles Project of Intelligent Link
#556of 1084 in China#655of 1339 in Verra (VCS)#4of 16 in AMS-III.C
Audit Analysis
A VCS transport project (electric commercial vehicles in China) with a confirmed investment additionality test and a registered status, but significant concerns around a 43% under-delivery against the pro-rata lifetime expectation, an unaddressed leakage justification, and the absence of a buffer pool. The verification process generated 23 corrective action requests (all closed), and multiple contradictions exist between the PDD, validation, and verification reports on safeguards, benefit sharing, and leakage treatment.
Red Flags
- Verified ERR of 25,105 tCO2e represents only ~43% of the pro-rata lifetime expectation (~57,800 tCO2e for the 1.54-year monitoring period out of 10 years), indicating substantial under-delivery
- Leakage deduction of 0% with justification listed as 'not addressed' in the validation report, contradicting the PDD's 'deemed negligible' claim — no quantified analysis found
- No buffer pool percentage stated and reversal events explicitly 'not addressed' in available documents
- 23 Corrective Action Requests raised during verification (all closed), suggesting significant initial documentation or methodology issues
- Safeguards, grievance mechanism, and benefit sharing are inconsistently reported across documents (present in validation, absent in verification)
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 199 | 112 | 87 | |
| 2022 | 14,613 | 0 | 14,613 | |
| 2023 | 10,293 | 0 | 10,293 | |
| Total | 25,105 | 112 | 24,993 |
Risk Indicators
VVB-confirmed investment test
reversals not addressed
0% deduction, justification not addressed
Project-specific; no reassessment date
Not confirmed in verification report
CORSIA-ineligible; CCP not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →