AMS-III.C — Emission reductions by electric and hybrid vehicles

About this methodology

Projects introduce electric or hybrid vehicles for passenger or freight transport. The method compares their emissions with the fossil-fuel vehicles they replace.

Version
16.0 · source ·
Status
Active at CDM / UNFCCC · source ·
Climate outcome
Emission reductions
Activity
Transport
Official page
cdm.unfccc.int ·
Also used by projects of
1 more

How methodology v3 reads projects of this type

What CarbonMeld reads

  • shown

    Grid emission factor: the methodology sets rules for it (AMS-III.C v16.0 project emission factor, p. 12). CarbonMeld reads it in the project's documents. CM-F-AMS-III-C-GRID-EF

    Link
  • A confirmed investment analysis A-INVEST

    The documents show a project-level additionality test, the validation confirmed it, and it is an investment analysis (a numeric test of the project's finances with and without carbon revenue).

Figures set against the methodology's own values

  • Integrity comparison

    The small-scale limit is 60 kt CO2e per year (p. 4). CarbonMeld compares the project's annual estimate with it. CM-F-AMS-III-C-SMALL-SCALE-LIMIT

    small-scale limit: 60 kt CO2e per year

    Link

Set by the methodology or the programme, not assessed by our current method

  • not assessed

    Usage rate of the devices: the methodology sets rules for it (AMS-III.C v16.0 Data / Parameter table 1 DDi, p. 13). Our current method does not assess it. CM-F-AMS-III-C-USAGE

    Link
  • not assessed

    Tracking of the end use: the methodology sets rules for it (AMS-III.C v16.0 applicability, p. 3). Our current method does not assess it. CM-F-AMS-III-C-END-USE-TRACKING

    Link
  • not assessed

    Social safeguards and consent of communities (FPIC): any such rules come from the programme, not the methodology. Our current method does not assess it. CM-F-AMS-III-C-SAFEGUARDS-FPIC

    Link

Not applicable to this type — never a gap in our current method

The criterion does not apply to this methodology. Our current method never counts it as a gap.

The general rules apply as well. Read the general rules.

The rules of methodology v2.2, as they were: the archived v2.2 page.

History and transitions

All 16 versions · current v16.0
  • v16.0adopted 8 Sept 2022currentsource

    Ensure the consistency in definitions of market penetration metrics and thresholds.

  • v15.0adopted 16 Apr 2015source

    To include the additional option based on electricity used for charging the vehicles for calculation of baseline emissions and project emissions.

  • v14.0adopted 28 Nov 2014source

    Expand applicability to include vehicle charging service providers and elaborate procedures for avoidance of double counting of emission reductions. Include additional options to determine specific fuel consumption of baseline vehicles.

  • v13.0adopted 3 Jun 2011source

    Include specific guidance for demonstrating additionality; Elaborate procedures for calculating baseline, project emissions and monitoring parameters.

  • v12.0adopted 30 Jul 2010source

    Clarify that the methodology is applicable for electric and hybrid vehicles; Under the PoA section leakage provisions pertaining to project activities involving fossil fuel switch measures has been excluded.

  • v11.0adopted 27 Jul 2007source

    Expand for application under a programme of activities (PoA).  This document, together with the ‘General Guidance’ and all other approved SSC methodologies, was part of a single document entitled: Appendix B of the Simplified Modalities …

  • v10.0adopted 15 Dec 2006source

    EB 28, Para 54 Remove the interim applicability condition i.e. 25 ktCO2e/yr limit from all Type III categories.

  • v09.0adopted 21 Jul 2006source

    Introduce provisions on the treatment of project emissions and include the respective monitoring requirements.

  • v08.0adopted 12 May 2006source

    Introduce the interim applicability condition, i.e. 25kt CO2e/yr limit for all Type III categories.

  • v07.0adopted 25 Nov 2005source

    References to “non-renewable biomass” in Appendix B deleted.

  • v06.0adopted 30 Sept 2005source

    Guidance on consideration of non-renewable biomass in Type I methodologies, thermal equivalence of Type II GWhe limits included.

  • v05.0adopted 25 Feb 2005source

    Guidance on ‘capacity addition’ and ‘cofiring’ in Type I methodologies and monitoring of methane in AMS-III.D included.

  • v04.0adopted 22 Oct 2004source

    AMS-II.F was adopted, leakage due to equipment transfer was included in all Type I and Type II methodologies.

  • v03.0adopted 14 Jun 2004source

    New methodology AMS-III.E was adopted.

  • v02.0adopted 28 Nov 2003source

    Definition of build margin included in AMS-I.D, minor revisions to AMS-I.A, AMS-III.D, AMS-II.E.

  • v01adopted 21 Jan 2003source

    Initial adoption. The Board at its seventh meeting noted the adoption by the Conference of the Parties (COP), by its decision 21/CP.8, of simplified modalities and procedures for small-scale CDM project activities (SSC M&P).

Projects using AMS-III.C

Browse 59 published projects using AMS-III.C, listed alphabetically. There is no ranking for this methodology yet: it appears here automatically once 5 of its projects not in the pipeline or under validation are rated. Open a project to view its registry details and the analysis available for that project.

Which registries list projects under AMS-III.C?

In CarbonMeld's data, AMS-III.C projects are on 5 registries: Verra (30), CDM (22) and Gold Standard (4), and 2 more. Being listed on a registry is not the same as being registered: the «Registered» column counts the projects each registry shows as registered, and credits are issued only after each verification.

RegistryProjectsRegisteredProjects list
Verra (VCS)3014See the list
CDM (UNFCCC)227See the list
Gold Standard (GS)42See the list
Universal Carbon Registry (UCR)22See the list
BioCarbon Registry (BCR)10See the list

Counts of project records in CarbonMeld's data, with or without a CarbonMeld analysis. «Registered» counts the records whose current registry status is «registered», as last read (24 November 2026); projects in a later status, such as awaiting verification approval, late to verify or completed, are not in that column.

5 of these projects have no number: additionality, quantification or both have no public grade of their type of project that applies to them yet. Their pages give the reason and how many negative facts were found; the analysis is in Premium.