Audit Analysis
A Gold Standard safe water project in Bangladesh that displaces fuel-based water heating, with VVB-confirmed additionality and fully verified emissions reductions for the 2023–2024 monitoring period. The project-specific baseline, 100% usage rate assumption, and absence of a buffer pool introduce moderate conservatism concerns, though these are partially offset by the inherently low permanence risk of an energy-efficiency activity. Multiple administrative corrective actions were raised but no substantive integrity issues were identified.
Red Flags
- Additionality test type is not stated in any available document, limiting the ability to assess the robustness of the additionality claim despite VVB confirmation
- 100% usage rate is both assumed and verified, leaving no margin for under-utilisation of the water purification technology
- No buffer pool or permanence mechanism is documented, though reversal risk is inherently low for an energy-efficiency project
- A 2023 verification report characterised leakage as 'quantified' while the 2024 report states it was 'deemed negligible' — the basis for the 0% deduction is not clearly documented
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 7,744 | 7,744 | 0 | |
| 2022 | 25,854 | 25,691 | 163 | |
| 2023 | 37,936 | 37,178 | 758 | |
| 2024 | 30,721 | 30,107 | 614 | |
| Total | 102,255 | 100,720 | 1,535 |
Risk Indicators
VVB-confirmed but test type not stated
Energy-efficiency project, no reversal risk
0% deduction, deemed negligible, not quantified
Project-specific, no reassessment date recorded
FPIC, grievance mechanism, benefit sharing documented
CORSIA and CCP status not stated; FAR raised
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →