GS1247 VPA 229 The Gambia Safe Water

GS-2187 ↗ · current registry ID: GS7585

#210of 1329 in Industrial#4of 8 in Gambia#366of 1801 in Gold Standard (GS)

5.5/ 10
Integrity
5.5
Transparency
6.0
Claim Safety
5.5
Documentation
5.0

Audit Analysis

The Gambia Safe Water project (GS1247 VPA 229) is a Gold Standard safe water project with VVB-confirmed additionality and no reported reversal events, but it is undermined by extensive material findings (21 CARs, multiple borehole water-quality failures), a 0% leakage deduction whose justification shifted between reports, and numerous contradictions across documents. The project delivered its claimed emissions reductions for the 2023–2024 monitoring period, but the absence of a buffer pool, the project-specific baseline, and the volume of unresolved corrective actions (including five open FARs) limit confidence in long-term integrity.

Red Flags

  • 19 boreholes failed water quality testing in Q1 2021 and 11 in Q2 2021 due to coliforms; 18 boreholes failed initial testing and required chlorination treatment — operational reliability of the water infrastructure is in question
  • Leakage deduction is 0% in the 2024 verification report, but the PDD (2023-06-29) specified a 5% deduction; the justification also shifted from 'deemed negligible' (2023) to 'quantified' (2024) without clear reconciliation
  • Five Forward Action Requests (FARs) remain open, including evaluation of SDG indicators at VPA level and submission of an fNRB report, indicating unresolved compliance gaps
  • Total ERR figures differ substantially between the 2023 verification report (claimed 60,000 / verified 65,901) and the 2024 report (claimed 36,083 / verified 36,083), and the basis for the difference is not clearly explained in the extracted record

Credit Vintages

IssuedRetiredAvailable
2020
3,5623,5620
2021
5,5995,494105
2022
5,7454,3831,362
2023
4,34604,346
Total19,25213,4395,813

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

borehole failures

Leakage

0% deduction; justification inconsistent

Baseline

Project-specific; reassessed 2024

Safeguards

FPIC, grievance, benefit sharing

Double-claim

CORSIA/CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-03General Methodology v2.1

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents